Alfurjan Package 6 construction progress

The register lists Alfurjan Package 6 in Al Furjan as complete, with a registered completion date of September 2016. Its last site inspection on record was in March 2017. The developer is Alfurjan.

100%

Built, at the site inspection of 19 March 2017

Construction complete

Registered completion date
September 2016
Construction started
October 2014
First registered
May 2015
Developer
Alfurjan
Community
Al Furjan
Units
151
Escrow bank
Mashreq Bank
Name in Arabic
الفرجان 6
Project number
1661
Site inspections
3

Schedule

The register lists Alfurjan Package 6 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 March 2017

100%+3.2 pts

  • Alfurjan Package 6 construction site, inspection photo 1, 19 March 2017
  • Alfurjan Package 6 construction site, inspection photo 2, 19 March 2017
  • Alfurjan Package 6 construction site, inspection photo 3, 19 March 2017
  • Alfurjan Package 6 construction site, inspection photo 4, 19 March 2017

11 October 2016

97%+26 pts

  • Alfurjan Package 6 construction site, inspection photo 1, 11 October 2016
  • Alfurjan Package 6 construction site, inspection photo 2, 11 October 2016
  • Alfurjan Package 6 construction site, inspection photo 3, 11 October 2016
  • Alfurjan Package 6 construction site, inspection photo 4, 11 October 2016

7 April 2016

71%

  • Alfurjan Package 6 construction site, inspection photo 1, 7 April 2016
  • Alfurjan Package 6 construction site, inspection photo 2, 7 April 2016
  • Alfurjan Package 6 construction site, inspection photo 3, 7 April 2016
  • Alfurjan Package 6 construction site, inspection photo 4, 7 April 2016

All 23 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Alfurjan Package 6?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Alfurjan Package 6 handover date?
Construction of Alfurjan Package 6 is recorded as complete, with a registered completion date of September 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Alfurjan Package 6?
Alfurjan Package 6 was 100% built at the site inspection on 19 March 2017. The site has been inspected 3 times since April 2016. The Land Department took 23 site photos at its inspections.
Is Alfurjan Package 6 delayed?
The register lists construction as complete.
Who is building Alfurjan Package 6?
The registered developer is Alfurjan.
Which bank holds the escrow account for Alfurjan Package 6?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.