Al Fouad construction progress

The register lists Al Fouad in Al Furjan as complete, with a registered completion date of December 2017. Its last site inspection on record was in April 2018. The developer is Sooma Real Estate Developer.

100%

Built, at the site inspection of 2 April 2018

Construction complete

Registered completion date
December 2017
Construction started
January 2016
First registered
April 2017
Developer
Sooma Real Estate Developer
Community
Al Furjan
Units
108
Escrow bank
Dubai Islamic Bank
Name in Arabic
الفؤاد
Project number
1858
Site inspections
2

Schedule

The register lists Al Fouad as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 April 2018

100%+4.0 pts

  • Al Fouad construction site, inspection photo 1, 2 April 2018
  • Al Fouad construction site, inspection photo 2, 2 April 2018
  • Al Fouad construction site, inspection photo 3, 2 April 2018
  • Al Fouad construction site, inspection photo 4, 2 April 2018

14 November 2017

96%

  • Al Fouad construction site, inspection photo 1, 14 November 2017
  • Al Fouad construction site, inspection photo 2, 14 November 2017
  • Al Fouad construction site, inspection photo 3, 14 November 2017
  • Al Fouad construction site, inspection photo 4, 14 November 2017

All 22 site photos, by inspection date

Context

Al Furjan has 38 projects under construction, 32% built on average.

Own a unit in Al Fouad?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Al Fouad handover date?
Construction of Al Fouad is recorded as complete, with a registered completion date of December 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Al Fouad?
Al Fouad was 100% built at the site inspection on 2 April 2018. The site has been inspected 2 times since November 2017. The Land Department took 22 site photos at its inspections.
Is Al Fouad delayed?
The register lists construction as complete.
Who is building Al Fouad?
The registered developer is Sooma Real Estate Developer.
Which bank holds the escrow account for Al Fouad?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.