South Garden E construction progress

The registered completion date for South Garden E in Wasl Gate is May 2028. At the last site inspection, in September 2026, it was 8.0% built. The developer is Jag Development.

8.0%

Built, at the site inspection of 7 September 2026

Running behind its date

Registered completion date
May 2028
Finish at recent pace
December 2031
Construction started
October 2025
First registered
June 2025
Community
Wasl Gate
Units
256
Escrow bank
Emirates NBD
Name in Arabic
E ساوث غاردن
Project number
3761
Site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 1.5 points a month. At that rate it would finish around December 2031, more than three months after its registered date of May 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 September 2026

8.0%+7.9 pts

  • South Garden E construction site, inspection photo 1, 7 September 2026
  • South Garden E construction site, inspection photo 2, 7 September 2026
  • South Garden E construction site, inspection photo 3, 7 September 2026
  • South Garden E construction site, inspection photo 4, 7 September 2026

27 March 2026

0.1%+0.1 pts

  • South Garden E construction site, inspection photo 1, 27 March 2026
  • South Garden E construction site, inspection photo 2, 27 March 2026
  • South Garden E construction site, inspection photo 3, 27 March 2026
  • South Garden E construction site, inspection photo 4, 27 March 2026

3 June 2025

0%

  • South Garden E construction site, inspection photo 1, 3 June 2025
  • South Garden E construction site, inspection photo 2, 3 June 2025

All 12 site photos, by inspection date

Context

Wasl Gate has 13 projects under construction, 21% built on average.

Jag Development has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in South Garden E?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the South Garden E handover date?
The registered completion date is May 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on South Garden E?
South Garden E was 8.0% built at the site inspection on 7 September 2026. The site has been inspected 3 times since June 2025. The Land Department took 12 site photos at its inspections.
Is South Garden E delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building South Garden E?
The registered developer is Jag Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for South Garden E?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.