South Garden E construction progress

South Garden E in Wasl Gate is 8.0% built at the Land Department inspection of September 2026. Developer Jag Development. Completion registered for May 2028.

8.0%

Built, at the Land Department site inspection of 7 September 2026

Running behind its date

Completion date (Land Department)
May 2028
Finish at recent pace
December 2031
Construction started
October 2025
Registered with the Land Department
June 2025
Community
Wasl Gate
Units
256
Escrow bank
Emirates NBD
Name in Arabic
E ساوث غاردن
Land Department project number
3761
Land Department site inspections
3

Schedule

Between March 2026 and September 2026 the site added about 1.5 points a month. At that rate it would finish around December 2031, more than three months after the May 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 September 2026

8.0%+7.9 pts

  • South Garden E construction site, Land Department inspection photo 1, 7 September 2026
  • South Garden E construction site, Land Department inspection photo 2, 7 September 2026
  • South Garden E construction site, Land Department inspection photo 3, 7 September 2026
  • South Garden E construction site, Land Department inspection photo 4, 7 September 2026

27 March 2026

0.1%+0.1 pts

  • South Garden E construction site, Land Department inspection photo 1, 27 March 2026
  • South Garden E construction site, Land Department inspection photo 2, 27 March 2026
  • South Garden E construction site, Land Department inspection photo 3, 27 March 2026
  • South Garden E construction site, Land Department inspection photo 4, 27 March 2026

3 June 2025

0%

  • South Garden E construction site, Land Department inspection photo 1, 3 June 2025
  • South Garden E construction site, Land Department inspection photo 2, 3 June 2025

All 12 site photos, by inspection date

Context

Wasl Gate has 13 projects under construction, 19% built on average.

Jag Development has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in South Garden E?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will South Garden E be completed?
The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around December 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of South Garden E is built?
8.0%, measured at the Land Department site inspection on 7 September 2026. The Land Department engineers have inspected the site 3 times since June 2025.
Is South Garden E delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
Who is building South Garden E?
The registered developer is Jag Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for South Garden E?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.