South Garden C construction progress
South Garden C in Wasl Gate is 16% built at the Land Department inspection of September 2026. Developer Jag Development. Completion registered for December 2027.
16%
Built, at the Land Department site inspection of 7 September 2026
Running behind its date
- Completion date (Land Department)
- December 2027
- Finish at recent pace
- February 2032
- Construction started
- January 2025
- Registered with the Land Department
- September 2024
- Developer
- Jag Development
- Community
- Wasl Gate
- Units
- 258
- Escrow bank
- Emirates NBD
- Name in Arabic
- C ساوث غاردن
- Land Department project number
- 3141
- Land Department site inspections
- 4
Schedule
Between February 2026 and September 2026 the site added about 1.3 points a month. At that rate it would finish around February 2032, more than three months after the December 2027 date registered with the Land Department.
Site inspections
7 September 2026
16%+8.2 pts
24 February 2026
8.0%+7.4 pts
21 July 2025
0.6%+0.6 pts
6 August 2024
0%
Context
Wasl Gate has 13 projects under construction, 19% built on average.
Jag Development has 12 projects under construction in Dubai, none past their registered completion dates.
Own a unit in South Garden C?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will South Garden C be completed?
- The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around February 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of South Garden C is built?
- 16%, measured at the Land Department site inspection on 7 September 2026. The Land Department engineers have inspected the site 4 times since August 2024.
- Is South Garden C delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building South Garden C?
- The registered developer is Jag Development. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for South Garden C?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Hillside Residences 1Also by Jag Development. 26%.
- Hillside Residences 2Also by Jag Development. 18%.
- Hillside Residences 3Also by Jag Development. 13%.
- South Garden AAlso by Jag Development. 16%.
- Hammock ParkNearby in Wasl Gate. 82%.
- Bellavion By SunriseNearby in Wasl Gate. 10%.
- Sola ResidencesNearby in Wasl Gate. 24%, Due September 2027.
- Hills View At Wasl GateNearby in Wasl Gate. 9.1%, Due June 2028.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)