Skip to content

Park Gate Residences construction progress

The register lists Park Gate Residences in Wasl 1 as complete, with a registered completion date of October 2020. Its last site inspection on record was in November 2020. The developer is Park 1.

100%

Built, at the site inspection of 23 November 2020

Construction complete

Registered completion date
October 2020
Construction started
August 2017
First registered
September 2017
Developer
Park 1
Community
Wasl 1
Units
764
Escrow bank
Emirates NBD
Name in Arabic
بارك جيت رازيدنس
Project number
1957
Site inspections
8

Schedule

The register lists Park Gate Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 November 2020

100%+12 pts

  • Park Gate Residences construction site, inspection photo 1, 23 November 2020
  • Park Gate Residences construction site, inspection photo 2, 23 November 2020
  • Park Gate Residences construction site, inspection photo 3, 23 November 2020
  • Park Gate Residences construction site, inspection photo 4, 23 November 2020

16 June 2020

88%+19 pts

  • Park Gate Residences construction site, inspection photo 1, 16 June 2020
  • Park Gate Residences construction site, inspection photo 2, 16 June 2020
  • Park Gate Residences construction site, inspection photo 3, 16 June 2020
  • Park Gate Residences construction site, inspection photo 4, 16 June 2020

19 December 2019

69%+18 pts

  • Park Gate Residences construction site, inspection photo 1, 19 December 2019
  • Park Gate Residences construction site, inspection photo 2, 19 December 2019
  • Park Gate Residences construction site, inspection photo 3, 19 December 2019
  • Park Gate Residences construction site, inspection photo 4, 19 December 2019

30 July 2019

50%+16 pts

  • Park Gate Residences construction site, inspection photo 1, 30 July 2019
  • Park Gate Residences construction site, inspection photo 2, 30 July 2019
  • Park Gate Residences construction site, inspection photo 3, 30 July 2019
  • Park Gate Residences construction site, inspection photo 4, 30 July 2019

21 March 2019

35%+13 pts

  • Park Gate Residences construction site, inspection photo 1, 21 March 2019
  • Park Gate Residences construction site, inspection photo 2, 21 March 2019
  • Park Gate Residences construction site, inspection photo 3, 21 March 2019
  • Park Gate Residences construction site, inspection photo 4, 21 March 2019

28 November 2018

21%+6.3 pts

  • Park Gate Residences construction site, inspection photo 1, 28 November 2018
  • Park Gate Residences construction site, inspection photo 2, 28 November 2018
  • Park Gate Residences construction site, inspection photo 3, 28 November 2018
  • Park Gate Residences construction site, inspection photo 4, 28 November 2018

18 July 2018

15%+7.2 pts

  • Park Gate Residences construction site, inspection photo 1, 18 July 2018
  • Park Gate Residences construction site, inspection photo 2, 18 July 2018
  • Park Gate Residences construction site, inspection photo 3, 18 July 2018
  • Park Gate Residences construction site, inspection photo 4, 18 July 2018

21 February 2018

7.6%

  • Park Gate Residences construction site, inspection photo 1, 21 February 2018
  • Park Gate Residences construction site, inspection photo 2, 21 February 2018
  • Park Gate Residences construction site, inspection photo 3, 21 February 2018
  • Park Gate Residences construction site, inspection photo 4, 21 February 2018

All 80 site photos, by inspection date

Context

Wasl 1 has 2 projects under construction, 52% built on average.

Park 1 has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Park Gate Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Park Gate Residences handover date?
Construction of Park Gate Residences is recorded as complete, with a registered completion date of October 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Park Gate Residences?
Park Gate Residences was 100% built at the site inspection on 23 November 2020. The site has been inspected 8 times since February 2018. The Land Department took 80 site photos at its inspections.
Is Park Gate Residences delayed?
The register lists construction as complete.
Who is building Park Gate Residences?
The registered developer is Park 1. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Park Gate Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.