Nine Collective construction progress
Nine Collective is 0% built at the Land Department inspection of August 2026. Developer Park 1. Completion registered for April 2030.
0%
Built, at the Land Department site inspection of 3 August 2026
Running behind its date
- Completion date (Land Department)
- April 2030
- Construction started
- July 2026
- Registered with the Land Department
- February 2026
- Developer
- Park 1
- Units
- 218
- Escrow bank
- Emirates NBD
- Name in Arabic
- ناين كوليكتيف
- Land Department project number
- 4315
- Land Department site inspections
- 2
Schedule
Site inspections
3 August 2026
0%
31 December 2025
0%
Context
Park 1 has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Nine Collective?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Nine Collective be completed?
- The completion date registered with the Dubai Land Department is April 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nine Collective is built?
- 0%, measured at the Land Department site inspection on 3 August 2026. The Land Department engineers have inspected the site 2 times since December 2025.
- Is Nine Collective delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2030.
- Who is building Nine Collective?
- The registered developer is Park 1. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Nine Collective?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Park Views Residences BAlso by Park 1. 99%, Due March 2027.
- Park Views Residences AAlso by Park 1. 96%.
- Avenue Park TowersAlso by Park 1. 7.7%, Due December 2028.
- Avenue Park Towers IiAlso by Park 1. 0%.
- Deyaar ParkNearby in . 0%, Due December 2012, passed.
- Varazze TowerNearby in . 92%, Due February 2024, passed.
- Niki Lauda TowerNearby in . 0.4%.
- Champions Tower2Nearby in . 78%, Due October 2017, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.