Avenue Park Towers construction progress

The registered completion date for Avenue Park Towers in Wasl 1 is December 2028. At the last site inspection, in September 2026, it was 7.7% built. The developer is Park 1.

7.7%

Built, at the site inspection of 8 September 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
February 2037
Construction started
August 2025
First registered
November 2024
Developer
Park 1
Community
Wasl 1
Units
671
Escrow bank
Emirates NBD
Name in Arabic
افينيو بارك تاورز
Project number
3337
Site inspections
3

Schedule

Between February 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around February 2037, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 September 2026

7.7%+4.9 pts

  • Avenue Park Towers construction site, inspection photo 1, 8 September 2026
  • Avenue Park Towers construction site, inspection photo 2, 8 September 2026
  • Avenue Park Towers construction site, inspection photo 3, 8 September 2026
  • Avenue Park Towers construction site, inspection photo 4, 8 September 2026

19 February 2026

2.8%+2.8 pts

  • Avenue Park Towers construction site, inspection photo 1, 19 February 2026
  • Avenue Park Towers construction site, inspection photo 2, 19 February 2026
  • Avenue Park Towers construction site, inspection photo 3, 19 February 2026
  • Avenue Park Towers construction site, inspection photo 4, 19 February 2026

30 October 2024

0%

  • Avenue Park Towers construction site, inspection photo 1, 30 October 2024
  • Avenue Park Towers construction site, inspection photo 2, 30 October 2024

All 13 site photos, by inspection date

Context

Wasl 1 has 2 projects under construction, 52% built on average.

Park 1 has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Avenue Park Towers?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Avenue Park Towers handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Avenue Park Towers?
Avenue Park Towers was 7.7% built at the site inspection on 8 September 2026. The site has been inspected 3 times since October 2024. The Land Department took 13 site photos at its inspections.
Is Avenue Park Towers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Avenue Park Towers?
The registered developer is Park 1. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Avenue Park Towers?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.