Avenue Park Towers construction progress

Avenue Park Towers in Wasl 1 is 7.7% built at the Land Department inspection of September 2026. Developer Park 1. Completion registered for December 2028.

7.7%

Built, at the Land Department site inspection of 8 September 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
February 2037
Construction started
August 2025
Registered with the Land Department
November 2024
Developer
Park 1
Community
Wasl 1
Units
671
Escrow bank
Emirates NBD
Name in Arabic
افينيو بارك تاورز
Land Department project number
3337
Land Department site inspections
3

Schedule

Between February 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around February 2037, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 September 2026

7.7%+4.9 pts

  • Avenue Park Towers construction site, Land Department inspection photo 1, 8 September 2026
  • Avenue Park Towers construction site, Land Department inspection photo 2, 8 September 2026
  • Avenue Park Towers construction site, Land Department inspection photo 3, 8 September 2026
  • Avenue Park Towers construction site, Land Department inspection photo 4, 8 September 2026

19 February 2026

2.8%+2.8 pts

  • Avenue Park Towers construction site, Land Department inspection photo 1, 19 February 2026
  • Avenue Park Towers construction site, Land Department inspection photo 2, 19 February 2026
  • Avenue Park Towers construction site, Land Department inspection photo 3, 19 February 2026
  • Avenue Park Towers construction site, Land Department inspection photo 4, 19 February 2026

30 October 2024

0%

  • Avenue Park Towers construction site, Land Department inspection photo 1, 30 October 2024
  • Avenue Park Towers construction site, Land Department inspection photo 2, 30 October 2024

All 13 site photos, by inspection date

Context

Wasl 1 has 3 projects under construction, 67% built on average.

Park 1 has 5 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Avenue Park Towers?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Avenue Park Towers be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around February 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Avenue Park Towers is built?
7.7%, measured at the Land Department site inspection on 8 September 2026. The Land Department engineers have inspected the site 3 times since October 2024.
Is Avenue Park Towers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Avenue Park Towers?
The registered developer is Park 1. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Avenue Park Towers?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.