Avenue Park Towers construction progress
The registered completion date for Avenue Park Towers in Wasl 1 is December 2028. At the last site inspection, in September 2026, it was 7.7% built. The developer is Park 1.
7.7%
Built, at the site inspection of 8 September 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- February 2037
- Construction started
- August 2025
- First registered
- November 2024
- Developer
- Park 1
- Community
- Wasl 1
- Units
- 671
- Escrow bank
- Emirates NBD
- Name in Arabic
- افينيو بارك تاورز
- Project number
- 3337
- Site inspections
- 3
Schedule
Between February 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around February 2037, more than three months after its registered date of December 2028.
Site inspections
8 September 2026
7.7%+4.9 pts
19 February 2026
2.8%+2.8 pts
30 October 2024
0%
Context
Wasl 1 has 2 projects under construction, 52% built on average.
Park 1 has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Avenue Park Towers?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Avenue Park Towers handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Avenue Park Towers?
- Avenue Park Towers was 7.7% built at the site inspection on 8 September 2026. The site has been inspected 3 times since October 2024. The Land Department took 13 site photos at its inspections.
- Is Avenue Park Towers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Avenue Park Towers?
- The registered developer is Park 1. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Avenue Park Towers?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Park Views Residences AAlso by Park 1. 96%.
- Nine CollectiveAlso by Park 1. 0%, Due April 2030.
- Avenue Park Towers IIAlso by Park 1. 0%, Due March 2030.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.