Park Views Residences A construction progress
No completion date is registered for Park Views Residences A in Wasl 1 yet. At the last site inspection, in September 2026, it was 96% built. The developer is Park 1.
96%
Built, at the site inspection of 8 September 2026
- Finish at recent pace
- November 2026
- Construction started
- July 2023
- First registered
- February 2024
- Developer
- Park 1
- Community
- Wasl 1
- Units
- 615
- Escrow bank
- Emirates NBD
- Name in Arabic
- A بارك فيوز ريزيدنسيز
- Project number
- 2630
- Site inspections
- 6
Schedule
Since February 2026 Park Views Residences A has added about 2.4 points a month. At that rate the site reaches 100% around November 2026. No completion date is on record to compare it with.
Site inspections
8 September 2026
96%+16 pts
20 February 2026
80%+35 pts
8 May 2025
45%+21 pts
2 December 2024
24%+13 pts
7 May 2024
11%+11 pts
5 April 2023
0%
Context
Wasl 1 has 2 projects under construction, 52% built on average.
Park 1 has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Park Views Residences A?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Park Views Residences A handover date?
- No completion date is on record for Park Views Residences A yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Park Views Residences A?
- Park Views Residences A was 96% built at the site inspection on 8 September 2026. The site has been inspected 6 times since April 2023. The Land Department took 38 site photos at its inspections.
- Who is building Park Views Residences A?
- The registered developer is Park 1. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Park Views Residences A?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Avenue Park TowersAlso by Park 1. 7.7%, Due December 2028.
- Nine CollectiveAlso by Park 1. 0%, Due April 2030.
- Avenue Park Towers IIAlso by Park 1. 0%, Due March 2030.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.