Park Views Residences A construction progress
Park Views Residences A in Wasl 1 is 96% built at the Land Department inspection of September 2026. Developer Park 1.
96%
Built, at the Land Department site inspection of 8 September 2026
Schedule
Since February 2026 Park Views Residences A has added about 2.4 points a month. At that rate the site reaches 100% around November 2026. The Land Department has no completion date on record to compare it with.
Site inspections
8 September 2026
96%+16 pts
20 February 2026
80%+35 pts
8 May 2025
45%+21 pts
2 December 2024
24%+13 pts
7 May 2024
11%+11 pts
5 April 2023
0%
Context
Wasl 1 has 3 projects under construction, 67% built on average.
Park 1 has 5 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Park Views Residences A?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Park Views Residences A be completed?
- The Land Department has no completion date on record for Park Views Residences A yet.
- How much of Park Views Residences A is built?
- 96%, measured at the Land Department site inspection on 8 September 2026. The Land Department engineers have inspected the site 6 times since April 2023.
- Who is building Park Views Residences A?
- The registered developer is Park 1. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Park Views Residences A?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Park Views Residences BAlso by Park 1. 99%, Due March 2027.
- Avenue Park TowersAlso by Park 1. 7.7%, Due December 2028.
- Nine CollectiveAlso by Park 1. 0%, Due April 2030.
- Avenue Park Towers IiAlso by Park 1. 0%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.