Jomana construction progress

The register lists Jomana in Um Suqaim Third as complete, with a registered completion date of April 2026. Its last site inspection on record was in September 2026. The developer is Jumeirah Hills Development.

100%

Built, at the site inspection of 4 September 2026

Construction complete

Registered completion date
April 2026
Construction started
April 2023
First registered
March 2023
Units
326
Escrow bank
Emirates NBD
Name in Arabic
جومانه
Project number
2582
Site inspections
10

Schedule

The register lists Jomana as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 September 2026

100%+17 pts

  • Jomana construction site, inspection photo 1, 4 September 2026
  • Jomana construction site, inspection photo 2, 4 September 2026
  • Jomana construction site, inspection photo 3, 4 September 2026
  • Jomana construction site, inspection photo 4, 4 September 2026

20 May 2026

83%+12 pts

  • Jomana construction site, inspection photo 1, 20 May 2026
  • Jomana construction site, inspection photo 2, 20 May 2026
  • Jomana construction site, inspection photo 3, 20 May 2026
  • Jomana construction site, inspection photo 4, 20 May 2026

20 January 2026

72%+10 pts

  • Jomana construction site, inspection photo 1, 20 January 2026
  • Jomana construction site, inspection photo 2, 20 January 2026
  • Jomana construction site, inspection photo 3, 20 January 2026
  • Jomana construction site, inspection photo 4, 20 January 2026

17 October 2025

61%+16 pts

  • Jomana construction site, inspection photo 1, 17 October 2025
  • Jomana construction site, inspection photo 2, 17 October 2025
  • Jomana construction site, inspection photo 3, 17 October 2025
  • Jomana construction site, inspection photo 4, 17 October 2025

28 July 2025

46%+6.9 pts

  • Jomana construction site, inspection photo 1, 28 July 2025
  • Jomana construction site, inspection photo 2, 28 July 2025
  • Jomana construction site, inspection photo 3, 28 July 2025
  • Jomana construction site, inspection photo 4, 28 July 2025

29 April 2025

39%+18 pts

  • Jomana construction site, inspection photo 1, 29 April 2025
  • Jomana construction site, inspection photo 2, 29 April 2025
  • Jomana construction site, inspection photo 3, 29 April 2025
  • Jomana construction site, inspection photo 4, 29 April 2025

16 January 2025

21%+16 pts

  • Jomana construction site, inspection photo 1, 16 January 2025
  • Jomana construction site, inspection photo 2, 16 January 2025
  • Jomana construction site, inspection photo 3, 16 January 2025
  • Jomana construction site, inspection photo 4, 16 January 2025

23 September 2024

4.6%+4.3 pts

  • Jomana construction site, inspection photo 1, 23 September 2024
  • Jomana construction site, inspection photo 2, 23 September 2024
  • Jomana construction site, inspection photo 3, 23 September 2024
  • Jomana construction site, inspection photo 4, 23 September 2024

8 May 2024

0.4%+0.4 pts

  • Jomana construction site, inspection photo 1, 8 May 2024
  • Jomana construction site, inspection photo 2, 8 May 2024
  • Jomana construction site, inspection photo 3, 8 May 2024

14 February 2023

0%

  • Jomana construction site, inspection photo 1, 14 February 2023
  • Jomana construction site, inspection photo 2, 14 February 2023

All 78 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Jomana?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Jomana handover date?
Construction of Jomana is recorded as complete, with a registered completion date of April 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Jomana?
Jomana was 100% built at the site inspection on 4 September 2026. The site has been inspected 10 times since February 2023. The Land Department took 78 site photos at its inspections.
Is Jomana delayed?
The register lists construction as complete.
Who is building Jomana?
The registered developer is Jumeirah Hills Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Jomana?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.