78 photos from 10 site inspections, newest first. The percentage is how much of Jomana was built on the day of each visit.

4 September 2026100% built

20 May 202683% built

20 January 202672% built

17 October 202561% built

28 July 202546% built

29 April 202539% built

16 January 202521% built

23 September 20244.6% built

8 May 20240.4% built

14 February 20230% built

Back to Jomana construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.