Nourelle construction progress

Nourelle in Um Suqaim Third is 4.0% built at the Land Department inspection of July 2026. Developer Jumeirah Hills Development. Completion registered for March 2029.

4.0%

Built, at the Land Department site inspection of 14 July 2026

Running behind its date

Completion date (Land Department)
March 2029
Finish at recent pace
February 2046
Construction started
December 2025
Registered with the Land Department
October 2025
Units
236
Escrow bank
Mashreq Bank
Name in Arabic
نوريل
Land Department project number
4108
Land Department site inspections
3

Schedule

Between September 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around February 2046, more than three months after the March 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 July 2026

4.0%+3.9 pts

  • Nourelle construction site, Land Department inspection photo 1, 14 July 2026
  • Nourelle construction site, Land Department inspection photo 2, 14 July 2026
  • Nourelle construction site, Land Department inspection photo 3, 14 July 2026
  • Nourelle construction site, Land Department inspection photo 4, 14 July 2026

16 April 2026

0%+0.0 pts

  • Nourelle construction site, Land Department inspection photo 1, 16 April 2026
  • Nourelle construction site, Land Department inspection photo 2, 16 April 2026
  • Nourelle construction site, Land Department inspection photo 3, 16 April 2026

23 September 2025

0%

  • Nourelle construction site, Land Department inspection photo 1, 23 September 2025
  • Nourelle construction site, Land Department inspection photo 2, 23 September 2025

All 11 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 27% built on average. Nourelle is behind that average.

Jumeirah Hills Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Nourelle?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Nourelle be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around February 2046. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Nourelle is built?
4.0%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 3 times since September 2025.
Is Nourelle delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Nourelle?
The registered developer is Jumeirah Hills Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Nourelle?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.