Nourelle construction progress
Nourelle in Um Suqaim Third is 4.0% built at the Land Department inspection of July 2026. Developer Jumeirah Hills Development. Completion registered for March 2029.
4.0%
Built, at the Land Department site inspection of 14 July 2026
Running behind its date
- Completion date (Land Department)
- March 2029
- Finish at recent pace
- February 2046
- Construction started
- December 2025
- Registered with the Land Department
- October 2025
- Developer
- Jumeirah Hills Development
- Community
- Um Suqaim Third
- Units
- 236
- Escrow bank
- Mashreq Bank
- Name in Arabic
- نوريل
- Land Department project number
- 4108
- Land Department site inspections
- 3
Schedule
Between September 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around February 2046, more than three months after the March 2029 date registered with the Land Department.
Site inspections
14 July 2026
4.0%+3.9 pts
16 April 2026
0%+0.0 pts
23 September 2025
0%
Context
Um Suqaim Third has 3 projects under construction, 27% built on average. Nourelle is behind that average.
Jumeirah Hills Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Nourelle?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Nourelle be completed?
- The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around February 2046. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nourelle is built?
- 4.0%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 3 times since September 2025.
- Is Nourelle delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
- Who is building Nourelle?
- The registered developer is Jumeirah Hills Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Nourelle?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.