Riwa construction progress

No completion date is registered for Riwa in Um Suqaim Third yet. At the last site inspection, in November 2026, it was 30% built. The developer is Jumeirah Hills Development.

30%

Built, at the site inspection of 3 November 2026

Finish at recent pace
November 2028
Construction started
September 2024
First registered
April 2024
Units
244
Escrow bank
First Abu Dhabi Bank
Name in Arabic
روى
Project number
3021
Site inspections
9

Schedule

Since January 2026 Riwa has added about 2.9 points a month. At that rate the site reaches 100% around November 2028. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

3 November 2026

30%+18 pts

  • Riwa construction site, inspection photo 1, 3 November 2026
  • Riwa construction site, inspection photo 2, 3 November 2026
  • Riwa construction site, inspection photo 3, 3 November 2026
  • Riwa construction site, inspection photo 4, 3 November 2026

20 July 2026

13%+6.0 pts

  • Riwa construction site, inspection photo 1, 20 July 2026
  • Riwa construction site, inspection photo 2, 20 July 2026
  • Riwa construction site, inspection photo 3, 20 July 2026
  • Riwa construction site, inspection photo 4, 20 July 2026

30 April 2026

6.5%+3.2 pts

  • Riwa construction site, inspection photo 1, 30 April 2026
  • Riwa construction site, inspection photo 2, 30 April 2026
  • Riwa construction site, inspection photo 3, 30 April 2026
  • Riwa construction site, inspection photo 4, 30 April 2026

23 January 2026

3.3%+3.1 pts

  • Riwa construction site, inspection photo 1, 23 January 2026
  • Riwa construction site, inspection photo 2, 23 January 2026
  • Riwa construction site, inspection photo 3, 23 January 2026
  • Riwa construction site, inspection photo 4, 23 January 2026

23 October 2025

0.2%+0.2 pts

  • Riwa construction site, inspection photo 1, 23 October 2025
  • Riwa construction site, inspection photo 2, 23 October 2025
  • Riwa construction site, inspection photo 3, 23 October 2025
  • Riwa construction site, inspection photo 4, 23 October 2025

31 July 2025

0%

  • Riwa construction site, inspection photo 1, 31 July 2025
  • Riwa construction site, inspection photo 2, 31 July 2025
  • Riwa construction site, inspection photo 3, 31 July 2025
  • Riwa construction site, inspection photo 4, 31 July 2025

7 May 2025

0%

  • Riwa construction site, inspection photo 1, 7 May 2025
  • Riwa construction site, inspection photo 2, 7 May 2025
  • Riwa construction site, inspection photo 3, 7 May 2025

12 February 2025

0%

  • Riwa construction site, inspection photo 1, 12 February 2025
  • Riwa construction site, inspection photo 2, 12 February 2025
  • Riwa construction site, inspection photo 3, 12 February 2025

28 March 2024

0%

  • Riwa construction site, inspection photo 1, 28 March 2024

All 47 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Riwa?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Riwa handover date?
No completion date is on record for Riwa yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Riwa?
Riwa was 30% built at the site inspection on 3 November 2026. The site has been inspected 9 times since March 2024. The Land Department took 47 site photos at its inspections.
Who is building Riwa?
The registered developer is Jumeirah Hills Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Riwa?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.