Elara construction progress

Elara in Um Suqaim Third is 64% built at the Land Department inspection of July 2026. Developer Jumeirah Hills Development. Completion registered for November 2026.

64%

Built, at the Land Department site inspection of 20 July 2026

Running behind its date

Completion date (Land Department)
November 2026
Finish at recent pace
March 2027
Construction started
November 2023
Registered with the Land Department
September 2023
Units
238
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إلارا
Land Department project number
2754
Land Department site inspections
9

Schedule

Between July 2025 and July 2026 the site added about 4.8 points a month. At that rate it would finish around March 2027, more than three months after the November 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 July 2026

64%+11 pts

  • Elara construction site, Land Department inspection photo 1, 20 July 2026
  • Elara construction site, Land Department inspection photo 2, 20 July 2026
  • Elara construction site, Land Department inspection photo 3, 20 July 2026
  • Elara construction site, Land Department inspection photo 4, 20 July 2026

30 April 2026

54%+14 pts

  • Elara construction site, Land Department inspection photo 1, 30 April 2026
  • Elara construction site, Land Department inspection photo 2, 30 April 2026
  • Elara construction site, Land Department inspection photo 3, 30 April 2026
  • Elara construction site, Land Department inspection photo 4, 30 April 2026

30 January 2026

40%+18 pts

  • Elara construction site, Land Department inspection photo 1, 30 January 2026
  • Elara construction site, Land Department inspection photo 2, 30 January 2026
  • Elara construction site, Land Department inspection photo 3, 30 January 2026
  • Elara construction site, Land Department inspection photo 4, 30 January 2026

22 October 2025

22%+14 pts

  • Elara construction site, Land Department inspection photo 1, 22 October 2025
  • Elara construction site, Land Department inspection photo 2, 22 October 2025
  • Elara construction site, Land Department inspection photo 3, 22 October 2025
  • Elara construction site, Land Department inspection photo 4, 22 October 2025

31 July 2025

8.4%+7.8 pts

  • Elara construction site, Land Department inspection photo 1, 31 July 2025
  • Elara construction site, Land Department inspection photo 2, 31 July 2025
  • Elara construction site, Land Department inspection photo 3, 31 July 2025
  • Elara construction site, Land Department inspection photo 4, 31 July 2025

7 May 2025

0.6%+0.5 pts

  • Elara construction site, Land Department inspection photo 1, 7 May 2025
  • Elara construction site, Land Department inspection photo 2, 7 May 2025
  • Elara construction site, Land Department inspection photo 3, 7 May 2025

25 February 2025

0%+0.0 pts

  • Elara construction site, Land Department inspection photo 1, 25 February 2025
  • Elara construction site, Land Department inspection photo 2, 25 February 2025
  • Elara construction site, Land Department inspection photo 3, 25 February 2025

23 September 2024

0%

  • Elara construction site, Land Department inspection photo 1, 23 September 2024
  • Elara construction site, Land Department inspection photo 2, 23 September 2024
  • Elara construction site, Land Department inspection photo 3, 23 September 2024

5 September 2023

0%

  • Elara construction site, Land Department inspection photo 1, 5 September 2023
  • Elara construction site, Land Department inspection photo 2, 5 September 2023
  • Elara construction site, Land Department inspection photo 3, 5 September 2023

All 54 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 27% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Elara?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Elara be completed?
The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around March 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Elara is built?
64%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 9 times since September 2023.
Is Elara delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2026.
Who is building Elara?
The registered developer is Jumeirah Hills Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Elara?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.