Elara construction progress

Elara in Um Suqaim Third was registered to complete in November 2026 and is still under construction. At the last site inspection, in November 2026, it was 78% built. The developer is Jumeirah Hills Development.

78%

Built, at the site inspection of 3 November 2026

0 months past its registered completion date

Registered completion date
November 2026
Finish at recent pace
April 2027
Construction started
November 2023
First registered
September 2023
Units
238
Escrow bank
First Abu Dhabi Bank
Name in Arabic
إلارا
Project number
2754
Site inspections
10

Schedule

Elara was registered to complete in November 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.2 points a month. Kept at that rate, the site would reach 100% around April 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 November 2026

78%+14 pts

  • Elara construction site, inspection photo 1, 3 November 2026
  • Elara construction site, inspection photo 2, 3 November 2026
  • Elara construction site, inspection photo 3, 3 November 2026
  • Elara construction site, inspection photo 4, 3 November 2026

20 July 2026

64%+11 pts

  • Elara construction site, inspection photo 1, 20 July 2026
  • Elara construction site, inspection photo 2, 20 July 2026
  • Elara construction site, inspection photo 3, 20 July 2026
  • Elara construction site, inspection photo 4, 20 July 2026

30 April 2026

54%+14 pts

  • Elara construction site, inspection photo 1, 30 April 2026
  • Elara construction site, inspection photo 2, 30 April 2026
  • Elara construction site, inspection photo 3, 30 April 2026
  • Elara construction site, inspection photo 4, 30 April 2026

30 January 2026

40%+18 pts

  • Elara construction site, inspection photo 1, 30 January 2026
  • Elara construction site, inspection photo 2, 30 January 2026
  • Elara construction site, inspection photo 3, 30 January 2026
  • Elara construction site, inspection photo 4, 30 January 2026

22 October 2025

22%+14 pts

  • Elara construction site, inspection photo 1, 22 October 2025
  • Elara construction site, inspection photo 2, 22 October 2025
  • Elara construction site, inspection photo 3, 22 October 2025
  • Elara construction site, inspection photo 4, 22 October 2025

31 July 2025

8.4%+7.8 pts

  • Elara construction site, inspection photo 1, 31 July 2025
  • Elara construction site, inspection photo 2, 31 July 2025
  • Elara construction site, inspection photo 3, 31 July 2025
  • Elara construction site, inspection photo 4, 31 July 2025

7 May 2025

0.6%+0.5 pts

  • Elara construction site, inspection photo 1, 7 May 2025
  • Elara construction site, inspection photo 2, 7 May 2025
  • Elara construction site, inspection photo 3, 7 May 2025

25 February 2025

0%+0.0 pts

  • Elara construction site, inspection photo 1, 25 February 2025
  • Elara construction site, inspection photo 2, 25 February 2025
  • Elara construction site, inspection photo 3, 25 February 2025

23 September 2024

0%

  • Elara construction site, inspection photo 1, 23 September 2024
  • Elara construction site, inspection photo 2, 23 September 2024
  • Elara construction site, inspection photo 3, 23 September 2024

5 September 2023

0%

  • Elara construction site, inspection photo 1, 5 September 2023
  • Elara construction site, inspection photo 2, 5 September 2023
  • Elara construction site, inspection photo 3, 5 September 2023

All 63 site photos, by inspection date

Context

Um Suqaim Third has 3 projects under construction, 38% built on average.

Jumeirah Hills Development has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Elara?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Elara handover date?
The registered completion date was November 2026, and the register still lists Elara as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Elara?
Elara was 78% built at the site inspection on 3 November 2026. The site has been inspected 10 times since September 2023. The Land Department took 63 site photos at its inspections.
Is Elara delayed?
Yes. Its registered completion date of November 2026 has passed and the project is still listed as under construction.
Who is building Elara?
The registered developer is Jumeirah Hills Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Elara?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.