Jumeirah Residences Emirates Towers construction progress

The registered completion date for Jumeirah Residences Emirates Towers in Trade Center Second is September 2030. At the last site inspection, in September 2026, it was 4.2% built. The developer is Dhre 2 Bts.

4.2%

Built, at the site inspection of 28 September 2026

Running behind its date

Registered completion date
September 2030
Finish at recent pace
August 2038
Construction started
September 2025
First registered
July 2025
Developer
Dhre 2 Bts
Community
Trade Center Second
Units
754
Escrow bank
Mashreq Bank
Name in Arabic
جميرا ريزيدنسيز أبراج الإمارات
Project number
3820
Site inspections
4

Schedule

Between March 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around August 2038, more than three months after its registered date of September 2030.

0%25%50%75%100%20262027202820292030
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 September 2026

4.2%+2.9 pts

  • Jumeirah Residences Emirates Towers construction site, inspection photo 1, 28 September 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 2, 28 September 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 3, 28 September 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 4, 28 September 2026

22 June 2026

1.3%+1.3 pts

  • Jumeirah Residences Emirates Towers construction site, inspection photo 1, 22 June 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 2, 22 June 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 3, 22 June 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 4, 22 June 2026

23 March 2026

0%+0.0 pts

  • Jumeirah Residences Emirates Towers construction site, inspection photo 1, 23 March 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 2, 23 March 2026
  • Jumeirah Residences Emirates Towers construction site, inspection photo 3, 23 March 2026

2 July 2025

0%

  • Jumeirah Residences Emirates Towers construction site, inspection photo 1, 2 July 2025
  • Jumeirah Residences Emirates Towers construction site, inspection photo 2, 2 July 2025

All 14 site photos, by inspection date

Context

Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Jumeirah Residences Emirates Towers?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Jumeirah Residences Emirates Towers handover date?
The registered completion date is September 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Jumeirah Residences Emirates Towers?
Jumeirah Residences Emirates Towers was 4.2% built at the site inspection on 28 September 2026. The site has been inspected 4 times since July 2025. The Land Department took 14 site photos at its inspections.
Is Jumeirah Residences Emirates Towers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2030.
Who is building Jumeirah Residences Emirates Towers?
The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Jumeirah Residences Emirates Towers?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.