Jumeirah Residences Emirates Towers construction progress

Jumeirah Residences Emirates Towers in Trade Center Second is 4.2% built at the Land Department inspection of September 2026. Developer Dhre 2 Bts. Completion registered for September 2030.

4.2%

Built, at the Land Department site inspection of 28 September 2026

Running behind its date

Completion date (Land Department)
September 2030
Finish at recent pace
August 2038
Construction started
September 2025
Registered with the Land Department
July 2025
Developer
Dhre 2 Bts
Community
Trade Center Second
Units
754
Escrow bank
Mashreq Bank
Name in Arabic
جميرا ريزيدنسيز أبراج الإمارات
Land Department project number
3820
Land Department site inspections
4

Schedule

Between March 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around August 2038, more than three months after the September 2030 date registered with the Land Department.

0%25%50%75%100%20262027202820292030
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

28 September 2026

4.2%+2.9 pts

  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 1, 28 September 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 2, 28 September 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 3, 28 September 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 4, 28 September 2026

22 June 2026

1.3%+1.3 pts

  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 1, 22 June 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 2, 22 June 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 3, 22 June 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 4, 22 June 2026

23 March 2026

0%+0.0 pts

  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 1, 23 March 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 2, 23 March 2026
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 3, 23 March 2026

2 July 2025

0%

  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 1, 2 July 2025
  • Jumeirah Residences Emirates Towers construction site, Land Department inspection photo 2, 2 July 2025

All 14 site photos, by inspection date

Context

Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Jumeirah Residences Emirates Towers?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Jumeirah Residences Emirates Towers be completed?
The completion date registered with the Dubai Land Department is September 2030. At the pace of its recent inspections the site would reach 100% around August 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Jumeirah Residences Emirates Towers is built?
4.2%, measured at the Land Department site inspection on 28 September 2026. The Land Department engineers have inspected the site 4 times since July 2025.
Is Jumeirah Residences Emirates Towers delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2030.
Who is building Jumeirah Residences Emirates Towers?
The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Jumeirah Residences Emirates Towers?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.