Symphony construction photos
36 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Symphony was built on the day of each visit.
30 April 202673% built
15 December 202557% built
3 July 202536% built
24 February 202516% built
12 December 20247.4% built
19 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.