Lana On The Park construction progress
Lana On The Park in Town Square is 36% built at the Land Department inspection of September 2026. Developer Nshama Properties.
36%
Built, at the Land Department site inspection of 10 September 2026
- Finish at recent pace
- November 2028
- Construction started
- October 2024
- Registered with the Land Department
- May 2024
- Developer
- Nshama Properties
- Community
- Town Square
- Units
- 196
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- لانا أون ذا بارك
- Land Department project number
- 3049
- Land Department site inspections
- 6
Schedule
Since November 2025 Lana On The Park has added about 2.5 points a month. At that rate the site reaches 100% around November 2028. The Land Department has no completion date on record to compare it with.
Site inspections
10 September 2026
36%+14 pts
18 March 2026
21%+9.8 pts
13 November 2025
12%+5.5 pts
7 July 2025
6.2%+6.2 pts
8 January 2025
0%+0.0 pts
22 April 2024
0%
Context
Town Square has 19 projects under construction, 30% built on average.
Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Lana On The Park?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Lana On The Park be completed?
- The Land Department has no completion date on record for Lana On The Park yet.
- How much of Lana On The Park is built?
- 36%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 6 times since April 2024.
- Who is building Lana On The Park?
- The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
- Which bank holds the escrow account for Lana On The Park?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.







.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)