Lana On The Park construction progress

Lana On The Park in Town Square is 36% built at the Land Department inspection of September 2026. Developer Nshama Properties.

36%

Built, at the Land Department site inspection of 10 September 2026

Finish at recent pace
November 2028
Construction started
October 2024
Registered with the Land Department
May 2024
Community
Town Square
Units
196
Escrow bank
First Abu Dhabi Bank
Name in Arabic
لانا أون ذا بارك
Land Department project number
3049
Land Department site inspections
6

Schedule

Since November 2025 Lana On The Park has added about 2.5 points a month. At that rate the site reaches 100% around November 2028. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

10 September 2026

36%+14 pts

  • Lana On The Park construction site, Land Department inspection photo 1, 10 September 2026
  • Lana On The Park construction site, Land Department inspection photo 2, 10 September 2026
  • Lana On The Park construction site, Land Department inspection photo 3, 10 September 2026
  • Lana On The Park construction site, Land Department inspection photo 4, 10 September 2026

18 March 2026

21%+9.8 pts

  • Lana On The Park construction site, Land Department inspection photo 1, 18 March 2026
  • Lana On The Park construction site, Land Department inspection photo 2, 18 March 2026
  • Lana On The Park construction site, Land Department inspection photo 3, 18 March 2026
  • Lana On The Park construction site, Land Department inspection photo 4, 18 March 2026

13 November 2025

12%+5.5 pts

  • Lana On The Park construction site, Land Department inspection photo 1, 13 November 2025
  • Lana On The Park construction site, Land Department inspection photo 2, 13 November 2025
  • Lana On The Park construction site, Land Department inspection photo 3, 13 November 2025
  • Lana On The Park construction site, Land Department inspection photo 4, 13 November 2025

7 July 2025

6.2%+6.2 pts

  • Lana On The Park construction site, Land Department inspection photo 1, 7 July 2025
  • Lana On The Park construction site, Land Department inspection photo 2, 7 July 2025
  • Lana On The Park construction site, Land Department inspection photo 3, 7 July 2025
  • Lana On The Park construction site, Land Department inspection photo 4, 7 July 2025

8 January 2025

0%+0.0 pts

  • Lana On The Park construction site, Land Department inspection photo 1, 8 January 2025
  • Lana On The Park construction site, Land Department inspection photo 2, 8 January 2025
  • Lana On The Park construction site, Land Department inspection photo 3, 8 January 2025

22 April 2024

0%

  • Lana On The Park construction site, Land Department inspection photo 1, 22 April 2024
  • Lana On The Park construction site, Land Department inspection photo 2, 22 April 2024

All 33 site photos, by inspection date

Context

Town Square has 19 projects under construction, 30% built on average.

Nshama Properties has 23 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Lana On The Park?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lana On The Park be completed?
The Land Department has no completion date on record for Lana On The Park yet.
How much of Lana On The Park is built?
36%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 6 times since April 2024.
Who is building Lana On The Park?
The registered developer is Nshama Properties. It has 22 other projects under construction in Dubai.
Which bank holds the escrow account for Lana On The Park?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.