Lexington construction progress

The registered completion date for Lexington in Town Square is September 2027. At the last site inspection, in August 2026, it was 4.5% built. The developer is Nshama Properties.

4.5%

Built, at the site inspection of 13 August 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
September 2037
Construction started
May 2025
First registered
November 2024
Community
Town Square
Units
142
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ليكسينغتون
Project number
3364
Site inspections
3

Schedule

Between February 2026 and August 2026 the site added about 0.7 points a month. At that rate it would finish around September 2037, more than three months after its registered date of September 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 August 2026

4.5%+4.5 pts

  • Lexington construction site, inspection photo 1, 13 August 2026
  • Lexington construction site, inspection photo 2, 13 August 2026
  • Lexington construction site, inspection photo 3, 13 August 2026
  • Lexington construction site, inspection photo 4, 13 August 2026

3 February 2026

0%+0.0 pts

  • Lexington construction site, inspection photo 1, 3 February 2026
  • Lexington construction site, inspection photo 2, 3 February 2026
  • Lexington construction site, inspection photo 3, 3 February 2026
  • Lexington construction site, inspection photo 4, 3 February 2026

30 October 2024

0%

  • Lexington construction site, inspection photo 1, 30 October 2024
  • Lexington construction site, inspection photo 2, 30 October 2024

All 11 site photos, by inspection date

Context

Town Square has 18 projects under construction, 29% built on average.

Nshama Properties has 22 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Lexington?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lexington handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lexington?
Lexington was 4.5% built at the site inspection on 13 August 2026. The site has been inspected 3 times since October 2024. The Land Department took 11 site photos at its inspections.
Is Lexington delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Lexington?
The registered developer is Nshama Properties. It has 21 other projects under construction in Dubai.
Which bank holds the escrow account for Lexington?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.