Lexington construction photos

11 photos taken by Dubai Land Department engineers at 3 site inspections, newest first. The percentage is how much of Lexington was built on the day of each visit.

13 August 20264.5% built

3 February 20260% built

30 October 20240% built

Back to Lexington construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.