Fia construction photos
41 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Fia was built on the day of each visit.
17 September 202685% built
30 April 202648% built
9 January 202634% built
19 September 202521% built
24 April 202511% built
24 January 20253.6% built
8 March 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.