Sobha Hartland Estates - Townhouses construction progress
The register lists Sobha Hartland Estates - Townhouses in Sobha Hartland as complete, with a registered completion date of September 2021. Its last site inspection on record was in September 2021. The developer is Sobha.
100%
Built, at the site inspection of 8 September 2021
Construction complete
- Registered completion date
- September 2021
- Construction started
- December 2016
- First registered
- December 2016
- Developer
- Sobha
- Community
- Sobha Hartland
- Units
- 27
- Escrow bank
- Bank of Baroda
- Name in Arabic
- شوبا هارتلاند العقارية - تاون هاوس
- Project number
- 1837
- Site inspections
- 11
Schedule
The register lists Sobha Hartland Estates - Townhouses as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
8 September 2021
100%+4.0 pts
4 March 2021
96%+1.9 pts
5 March 2020
94%+2.5 pts
4 September 2019
92%+4.0 pts
5 May 2019
88%+7.4 pts
14 January 2019
80%+24 pts
8 August 2018
57%+24 pts
22 March 2018
32%+11 pts
25 December 2017
21%+2.0 pts
4 December 2017
19%+12 pts
Context
Sobha Hartland has 3 projects under construction, 82% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Hartland Estates - Townhouses?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Sobha Hartland Estates - Townhouses handover date?
- Construction of Sobha Hartland Estates - Townhouses is recorded as complete, with a registered completion date of September 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Sobha Hartland Estates - Townhouses?
- Sobha Hartland Estates - Townhouses was 100% built at the site inspection on 8 September 2021. The site has been inspected 11 times since July 2017. The Land Department took 103 site photos at its inspections.
- Is Sobha Hartland Estates - Townhouses delayed?
- The register lists construction as complete.
- Who is building Sobha Hartland Estates - Townhouses?
- The registered developer is Sobha. It has 27 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Hartland Estates - Townhouses?
- Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- The HighburyNearby in Sobha Hartland. 80%.
- Casa SereneNearby in Sobha Hartland. 74%, Due December 2024, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.