Sobha Hartland - Crest Grande construction progress

The register lists Sobha Hartland - Crest Grande in Sobha Hartland as complete, with a registered completion date of June 2026. Its last site inspection on record was in April 2026. The developer is Sobha.

100%

Built, at the site inspection of 13 April 2026

Construction complete

Registered completion date
June 2026
Construction started
September 2022
First registered
January 2023
Developer
Sobha
Units
985
Escrow bank
Bank of Baroda
Name in Arabic
شوبا هارتلاند كريست جراندي
Project number
2482
Site inspections
10

Schedule

The register lists Sobha Hartland - Crest Grande as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 April 2026

100%+5.3 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 13 April 2026
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 13 April 2026
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 13 April 2026
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 13 April 2026

21 October 2025

95%+11 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 21 October 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 21 October 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 21 October 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 21 October 2025

8 May 2025

84%+3.9 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 8 May 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 8 May 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 8 May 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 8 May 2025

16 January 2025

80%+10 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 16 January 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 16 January 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 16 January 2025
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 16 January 2025

30 September 2024

70%+23 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 30 September 2024
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 30 September 2024
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 30 September 2024
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 30 September 2024

22 March 2024

47%+15 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 22 March 2024
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 22 March 2024
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 22 March 2024
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 22 March 2024

24 October 2023

32%+14 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 24 October 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 24 October 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 24 October 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 24 October 2023

19 June 2023

18%+8.7 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 19 June 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 19 June 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 19 June 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 19 June 2023

21 February 2023

9.6%+3.5 pts

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 21 February 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 21 February 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 21 February 2023
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 21 February 2023

7 November 2022

6.0%

  • Sobha Hartland - Crest Grande construction site, inspection photo 1, 7 November 2022
  • Sobha Hartland - Crest Grande construction site, inspection photo 2, 7 November 2022
  • Sobha Hartland - Crest Grande construction site, inspection photo 3, 7 November 2022
  • Sobha Hartland - Crest Grande construction site, inspection photo 4, 7 November 2022

All 112 site photos, by inspection date

Context

Sobha Hartland has 3 projects under construction, 82% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Hartland - Crest Grande?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sobha Hartland - Crest Grande handover date?
Construction of Sobha Hartland - Crest Grande is recorded as complete, with a registered completion date of June 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sobha Hartland - Crest Grande?
Sobha Hartland - Crest Grande was 100% built at the site inspection on 13 April 2026. The site has been inspected 10 times since November 2022. The Land Department took 112 site photos at its inspections.
Is Sobha Hartland - Crest Grande delayed?
The register lists construction as complete.
Who is building Sobha Hartland - Crest Grande?
The registered developer is Sobha. It has 27 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Hartland - Crest Grande?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.