Sobha Creek Vistas Grande construction progress
The register lists Sobha Creek Vistas Grande in Sobha Hartland as complete, with a registered completion date of July 2025. Its last site inspection on record was in December 2024. The developer is Sobha.
100%
Built, at the site inspection of 27 December 2024
Construction complete
- Registered completion date
- July 2025
- Construction started
- June 2022
- First registered
- October 2022
- Developer
- Sobha
- Community
- Sobha Hartland
- Units
- 400
- Escrow bank
- Mashreq Bank
- Name in Arabic
- شوبا كريك فيستا جراندي
- Project number
- 2458
- Site inspections
- 8
Schedule
The register lists Sobha Creek Vistas Grande as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
27 December 2024
100%+2.9 pts
12 November 2024
97%+17 pts
3 July 2024
80%+29 pts
15 February 2024
51%+11 pts
19 October 2023
40%+12 pts
19 June 2023
28%+10 pts
9 February 2023
18%+11 pts
16 September 2022
7.1%
Context
Sobha Hartland has 3 projects under construction, 82% built on average.
Sobha has 27 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Sobha Creek Vistas Grande?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Sobha Creek Vistas Grande handover date?
- Construction of Sobha Creek Vistas Grande is recorded as complete, with a registered completion date of July 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Sobha Creek Vistas Grande?
- Sobha Creek Vistas Grande was 100% built at the site inspection on 27 December 2024. The site has been inspected 8 times since September 2022. The Land Department took 79 site photos at its inspections.
- Is Sobha Creek Vistas Grande delayed?
- The register lists construction as complete.
- Who is building Sobha Creek Vistas Grande?
- The registered developer is Sobha. It has 27 other projects under construction in Dubai.
- Which bank holds the escrow account for Sobha Creek Vistas Grande?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha Seahaven Tower AAlso by Sobha. 45%, Due April 2028.
- Verde By SobhaAlso by Sobha. 85%, Due June 2027.
- Sobha Creek Vista HeightsAlso by Sobha. 92%.
- Sobha Seahaven Tower B & CAlso by Sobha. 40%, Due October 2028.
- The HighburyNearby in Sobha Hartland. 80%.
- Casa SereneNearby in Sobha Hartland. 74%, Due December 2024, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)