Skip to content

Tria By Deyaar construction progress

Tria By Deyaar in Silicon Oasis is 94% built at the Land Department inspection of August 2026. Developer Deyaar Bay Real Estate Development. Completion registered for June 2025.

94%

Built, at the Land Department site inspection of 25 August 2026

15 months past its registered completion date

Completion date (Land Department)
June 2025
Finish at recent pace
November 2026
Construction started
August 2022
Registered with the Land Department
June 2022
Developer
Deyaar Bay Real Estate Development
Community
Silicon Oasis
Units
717
Escrow bank
Dubai Islamic Bank
Name in Arabic
تريا من ديار
Land Department project number
2403
Land Department site inspections
10

Schedule

Tria By Deyaar was registered to complete in June 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 1.9 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

25 August 2026

94%+0.7 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 25 August 2026
  • Tria By Deyaar construction site, Land Department inspection photo 2, 25 August 2026
  • Tria By Deyaar construction site, Land Department inspection photo 3, 25 August 2026
  • Tria By Deyaar construction site, Land Department inspection photo 4, 25 August 2026

3 August 2026

93%+6.2 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 3 August 2026
  • Tria By Deyaar construction site, Land Department inspection photo 2, 3 August 2026
  • Tria By Deyaar construction site, Land Department inspection photo 3, 3 August 2026
  • Tria By Deyaar construction site, Land Department inspection photo 4, 3 August 2026

24 April 2026

87%+7.0 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 24 April 2026
  • Tria By Deyaar construction site, Land Department inspection photo 2, 24 April 2026
  • Tria By Deyaar construction site, Land Department inspection photo 3, 24 April 2026
  • Tria By Deyaar construction site, Land Department inspection photo 4, 24 April 2026

13 January 2026

80%+28 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 13 January 2026
  • Tria By Deyaar construction site, Land Department inspection photo 2, 13 January 2026
  • Tria By Deyaar construction site, Land Department inspection photo 3, 13 January 2026
  • Tria By Deyaar construction site, Land Department inspection photo 4, 13 January 2026

10 July 2025

53%+8.4 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 10 July 2025
  • Tria By Deyaar construction site, Land Department inspection photo 2, 10 July 2025
  • Tria By Deyaar construction site, Land Department inspection photo 3, 10 July 2025
  • Tria By Deyaar construction site, Land Department inspection photo 4, 10 July 2025

7 February 2025

44%+16 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 7 February 2025
  • Tria By Deyaar construction site, Land Department inspection photo 2, 7 February 2025
  • Tria By Deyaar construction site, Land Department inspection photo 3, 7 February 2025
  • Tria By Deyaar construction site, Land Department inspection photo 4, 7 February 2025

22 July 2024

29%+15 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 22 July 2024
  • Tria By Deyaar construction site, Land Department inspection photo 2, 22 July 2024
  • Tria By Deyaar construction site, Land Department inspection photo 3, 22 July 2024
  • Tria By Deyaar construction site, Land Department inspection photo 4, 22 July 2024

13 March 2024

13%+8.6 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 13 March 2024
  • Tria By Deyaar construction site, Land Department inspection photo 2, 13 March 2024
  • Tria By Deyaar construction site, Land Department inspection photo 3, 13 March 2024
  • Tria By Deyaar construction site, Land Department inspection photo 4, 13 March 2024

2 August 2023

4.7%+4.6 pts

  • Tria By Deyaar construction site, Land Department inspection photo 1, 2 August 2023
  • Tria By Deyaar construction site, Land Department inspection photo 2, 2 August 2023
  • Tria By Deyaar construction site, Land Department inspection photo 3, 2 August 2023
  • Tria By Deyaar construction site, Land Department inspection photo 4, 2 August 2023

7 February 2023

0%

  • Tria By Deyaar construction site, Land Department inspection photo 1, 7 February 2023
  • Tria By Deyaar construction site, Land Department inspection photo 2, 7 February 2023
  • Tria By Deyaar construction site, Land Department inspection photo 3, 7 February 2023

All 77 site photos, by inspection date

Context

Silicon Oasis has 11 projects under construction, 32% built on average.

Own a unit in Tria By Deyaar?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Tria By Deyaar be completed?
The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Tria By Deyaar is built?
94%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 10 times since February 2023.
Is Tria By Deyaar delayed?
Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
Who is building Tria By Deyaar?
The registered developer is Deyaar Bay Real Estate Development.
Which bank holds the escrow account for Tria By Deyaar?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.