Tria By Deyaar construction progress
Tria By Deyaar in Silicon Oasis is 94% built at the Land Department inspection of August 2026. Developer Deyaar Bay Real Estate Development. Completion registered for June 2025.
94%
Built, at the Land Department site inspection of 25 August 2026
15 months past its registered completion date
- Completion date (Land Department)
- June 2025
- Finish at recent pace
- November 2026
- Construction started
- August 2022
- Registered with the Land Department
- June 2022
- Developer
- Deyaar Bay Real Estate Development
- Community
- Silicon Oasis
- Units
- 717
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- تريا من ديار
- Land Department project number
- 2403
- Land Department site inspections
- 10
Schedule
Tria By Deyaar was registered to complete in June 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 1.9 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
25 August 2026
94%+0.7 pts
3 August 2026
93%+6.2 pts
24 April 2026
87%+7.0 pts
13 January 2026
80%+28 pts
10 July 2025
53%+8.4 pts
7 February 2025
44%+16 pts
22 July 2024
29%+15 pts
13 March 2024
13%+8.6 pts
2 August 2023
4.7%+4.6 pts
7 February 2023
0%
Context
Silicon Oasis has 11 projects under construction, 32% built on average.
Own a unit in Tria By Deyaar?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Tria By Deyaar be completed?
- The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Tria By Deyaar is built?
- 94%, measured at the Land Department site inspection on 25 August 2026. The Land Department engineers have inspected the site 10 times since February 2023.
- Is Tria By Deyaar delayed?
- Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
- Who is building Tria By Deyaar?
- The registered developer is Deyaar Bay Real Estate Development.
- Which bank holds the escrow account for Tria By Deyaar?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- SerenovaNearby in Silicon Oasis. 1.6%, Due March 2028.
- Aura EliteNearby in Silicon Oasis. 44%, Due April 2026, passed.
- Oasiz 1 By DanubeNearby in Silicon Oasis. 30%, Due November 2027.
- Oasiz 2 By DanubeNearby in Silicon Oasis. 31%, Due November 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)










.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)