Skip to content

Lynx construction progress

The register lists Lynx in Silicon Oasis as complete, with a registered completion date of May 2018. Its last site inspection on record was in May 2018. The developer is Earth Developers.

100%

Built, at the site inspection of 22 May 2018

Construction complete

Registered completion date
May 2018
Construction started
December 2007
First registered
November 2008
Developer
Earth Developers
Community
Silicon Oasis
Units
237
Escrow bank
Commercial Bank of Dubai
Name in Arabic
لينكس
Project number
493
Site inspections
7

Schedule

The register lists Lynx as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%200820102012201420162018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 May 2018

100%+19 pts

  • Lynx construction site, inspection photo 1, 22 May 2018
  • Lynx construction site, inspection photo 2, 22 May 2018
  • Lynx construction site, inspection photo 3, 22 May 2018
  • Lynx construction site, inspection photo 4, 22 May 2018

26 October 2016

81%+12 pts

  • Lynx construction site, inspection photo 1, 26 October 2016
  • Lynx construction site, inspection photo 2, 26 October 2016
  • Lynx construction site, inspection photo 3, 26 October 2016
  • Lynx construction site, inspection photo 4, 26 October 2016

11 January 2016

69%+8.3 pts

  • Lynx construction site, inspection photo 1, 11 January 2016
  • Lynx construction site, inspection photo 2, 11 January 2016
  • Lynx construction site, inspection photo 3, 11 January 2016
  • Lynx construction site, inspection photo 4, 11 January 2016

25 March 2015

60%+14 pts

  • Lynx construction site, inspection photo 1, 25 March 2015
  • Lynx construction site, inspection photo 2, 25 March 2015
  • Lynx construction site, inspection photo 3, 25 March 2015
  • Lynx construction site, inspection photo 4, 25 March 2015

25 June 2014

46%

  • Lynx construction site, inspection photo 1, 25 June 2014
  • Lynx construction site, inspection photo 2, 25 June 2014
  • Lynx construction site, inspection photo 3, 25 June 2014
  • Lynx construction site, inspection photo 4, 25 June 2014

21 November 2013

46%+2.4 pts

  • Lynx construction site, inspection photo 1, 21 November 2013
  • Lynx construction site, inspection photo 2, 21 November 2013
  • Lynx construction site, inspection photo 3, 21 November 2013
  • Lynx construction site, inspection photo 4, 21 November 2013

23 June 2013

44%

  • Lynx construction site, inspection photo 1, 23 June 2013
  • Lynx construction site, inspection photo 2, 23 June 2013
  • Lynx construction site, inspection photo 3, 23 June 2013
  • Lynx construction site, inspection photo 4, 23 June 2013

All 83 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Own a unit in Lynx?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Lynx handover date?
Construction of Lynx is recorded as complete, with a registered completion date of May 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Lynx?
Lynx was 100% built at the site inspection on 22 May 2018. The site has been inspected 7 times since June 2013. The Land Department took 83 site photos at its inspections.
Is Lynx delayed?
The register lists construction as complete.
Who is building Lynx?
The registered developer is Earth Developers.
Which bank holds the escrow account for Lynx?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.