Skip to content

Altia One construction progress

The register lists Altia One in Silicon Oasis as complete, with a registered completion date of September 2025. Its last site inspection on record was in October 2025. The developer is Y A S Developers.

100%

Built, at the site inspection of 17 October 2025

Construction complete

Registered completion date
September 2025
Construction started
October 2023
First registered
July 2024
Developer
Y A S Developers
Community
Silicon Oasis
Units
123
Escrow bank
Mashreq Bank
Name in Arabic
ألتيا وان
Project number
3039
Site inspections
5

Schedule

The register lists Altia One as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 October 2025

100%+7.1 pts

  • Altia One construction site, inspection photo 1, 17 October 2025
  • Altia One construction site, inspection photo 2, 17 October 2025
  • Altia One construction site, inspection photo 3, 17 October 2025
  • Altia One construction site, inspection photo 4, 17 October 2025

11 July 2025

93%+20 pts

  • Altia One construction site, inspection photo 1, 11 July 2025
  • Altia One construction site, inspection photo 2, 11 July 2025
  • Altia One construction site, inspection photo 3, 11 July 2025
  • Altia One construction site, inspection photo 4, 11 July 2025

11 March 2025

73%+23 pts

  • Altia One construction site, inspection photo 1, 11 March 2025
  • Altia One construction site, inspection photo 2, 11 March 2025
  • Altia One construction site, inspection photo 3, 11 March 2025
  • Altia One construction site, inspection photo 4, 11 March 2025

8 November 2024

50%+26 pts

  • Altia One construction site, inspection photo 1, 8 November 2024
  • Altia One construction site, inspection photo 2, 8 November 2024
  • Altia One construction site, inspection photo 3, 8 November 2024
  • Altia One construction site, inspection photo 4, 8 November 2024

9 May 2024

24%

  • Altia One construction site, inspection photo 1, 9 May 2024
  • Altia One construction site, inspection photo 2, 9 May 2024
  • Altia One construction site, inspection photo 3, 9 May 2024
  • Altia One construction site, inspection photo 4, 9 May 2024

All 47 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Own a unit in Altia One?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Altia One handover date?
Construction of Altia One is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Altia One?
Altia One was 100% built at the site inspection on 17 October 2025. The site has been inspected 5 times since May 2024. The Land Department took 47 site photos at its inspections.
Is Altia One delayed?
The register lists construction as complete.
Who is building Altia One?
The registered developer is Y A S Developers.
Which bank holds the escrow account for Altia One?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.