The Element At Sobha One construction progress

The registered completion date for The Element At Sobha One in Ras Al Khor Industrial First is December 2029. At the last site inspection, in November 2026, it was 17% built. The developer is Sobha.

17%

Built, at the site inspection of 18 November 2026

Running behind its date

Registered completion date
December 2029
Finish at recent pace
November 2031
Construction started
May 2025
First registered
March 2025
Developer
Sobha
Units
401
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا ايليمنت في شوبا ون
Project number
3540
Site inspections
4

Schedule

Between March 2026 and November 2026 the site added about 1.4 points a month. At that rate it would finish around November 2031, more than three months after its registered date of December 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 November 2026

17%+5.9 pts

  • The Element At Sobha One construction site, inspection photo 1, 18 November 2026
  • The Element At Sobha One construction site, inspection photo 2, 18 November 2026
  • The Element At Sobha One construction site, inspection photo 3, 18 November 2026
  • The Element At Sobha One construction site, inspection photo 4, 18 November 2026

11 August 2026

11%+5.0 pts

  • The Element At Sobha One construction site, inspection photo 1, 11 August 2026
  • The Element At Sobha One construction site, inspection photo 2, 11 August 2026
  • The Element At Sobha One construction site, inspection photo 3, 11 August 2026

23 March 2026

6.1%+6.1 pts

  • The Element At Sobha One construction site, inspection photo 1, 23 March 2026
  • The Element At Sobha One construction site, inspection photo 2, 23 March 2026
  • The Element At Sobha One construction site, inspection photo 3, 23 March 2026

3 March 2025

0%

  • The Element At Sobha One construction site, inspection photo 1, 3 March 2025
  • The Element At Sobha One construction site, inspection photo 2, 3 March 2025

All 16 site photos, by inspection date

Context

Ras Al Khor Industrial First has 3 projects under construction, 38% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Element At Sobha One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Element At Sobha One handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Element At Sobha One?
The Element At Sobha One was 17% built at the site inspection on 18 November 2026. The site has been inspected 4 times since March 2025. The Land Department took 16 site photos at its inspections.
Is The Element At Sobha One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building The Element At Sobha One?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for The Element At Sobha One?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.