Viceroy Hotel Resorts Residences construction progress

The register lists Viceroy Hotel Resorts Residences in Palm Jumeirah as complete, with a registered completion date of November 2016. Its last site inspection on record was in December 2016. The developer is S K A I Zaya Real Estate Development.

100%

Built, at the site inspection of 4 December 2016

Construction complete

Registered completion date
November 2016
Construction started
May 2013
First registered
May 2013
Developer
S K A I Zaya Real Estate Development
Community
Palm Jumeirah
Units
708
Escrow bank
Industrial and Commercial Bank of Chaina Limited - Abu Dhabi Branch
Name in Arabic
مساكن فيسروى للفنادق والمنتجعات
Project number
1344
Site inspections
9

Schedule

The register lists Viceroy Hotel Resorts Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201420152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 December 2016

100%+9.0 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 4 December 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 4 December 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 4 December 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 4 December 2016

10 July 2016

91%+4.9 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 10 July 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 10 July 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 10 July 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 10 July 2016

25 April 2016

86%+9.2 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 25 April 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 25 April 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 25 April 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 25 April 2016

13 January 2016

77%+15 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 13 January 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 13 January 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 13 January 2016
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 13 January 2016

21 June 2015

62%+12 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 21 June 2015
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 21 June 2015
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 21 June 2015
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 21 June 2015

24 February 2015

50%+19 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 24 February 2015
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 24 February 2015
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 24 February 2015
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 24 February 2015

26 October 2014

31%+18 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 26 October 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 26 October 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 26 October 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 26 October 2014

29 May 2014

12%+8.1 pts

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 29 May 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 29 May 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 29 May 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 29 May 2014

22 January 2014

4.3%

  • Viceroy Hotel Resorts Residences construction site, inspection photo 1, 22 January 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 2, 22 January 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 3, 22 January 2014
  • Viceroy Hotel Resorts Residences construction site, inspection photo 4, 22 January 2014

All 91 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in Viceroy Hotel Resorts Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Viceroy Hotel Resorts Residences handover date?
Construction of Viceroy Hotel Resorts Residences is recorded as complete, with a registered completion date of November 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Viceroy Hotel Resorts Residences?
Viceroy Hotel Resorts Residences was 100% built at the site inspection on 4 December 2016. The site has been inspected 9 times since January 2014. The Land Department took 91 site photos at its inspections.
Is Viceroy Hotel Resorts Residences delayed?
The register lists construction as complete.
Who is building Viceroy Hotel Resorts Residences?
The registered developer is S K A I Zaya Real Estate Development.
Which bank holds the escrow account for Viceroy Hotel Resorts Residences?
Industrial and Commercial Bank of Chaina Limited - Abu Dhabi Branch. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.