Viceroy Hotel Resorts Residences construction photos

91 photos from 9 site inspections, newest first. The percentage is how much of Viceroy Hotel Resorts Residences was built on the day of each visit.

4 December 2016100% built

10 July 201691% built

25 April 201686% built

13 January 201677% built

21 June 201562% built

24 February 201550% built

26 October 201431% built

29 May 201412% built

22 January 20144.3% built

Back to Viceroy Hotel Resorts Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.