The Alba Residences By Omniyat construction progress
The registered completion date for The Alba Residences By Omniyat in Palm Jumeirah is March 2028. At the last site inspection, in September 2026, it was 8.3% built. The developer is Grandeur Beach Real Estate Development.
8.3%
Built, at the site inspection of 1 September 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- October 2052
- Construction started
- July 2024
- First registered
- July 2024
- Developer
- Grandeur Beach Real Estate Development
- Community
- Palm Jumeirah
- Units
- 138
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا ألبا ريزيدنسز من أمنيات
- Project number
- 2987
- Site inspections
- 5
Schedule
Between October 2025 and September 2026 the site added about 0.3 points a month. At that rate it would finish around October 2052, more than three months after its registered date of March 2028.
Site inspections
1 September 2026
8.3%+1.3 pts
10 March 2026
7.0%+1.6 pts
30 October 2025
5.4%+3.6 pts
15 July 2025
1.8%+1.8 pts
3 July 2024
0%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Own a unit in The Alba Residences By Omniyat?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Alba Residences By Omniyat handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2052. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Alba Residences By Omniyat?
- The Alba Residences By Omniyat was 8.3% built at the site inspection on 1 September 2026. The site has been inspected 5 times since July 2024. The Land Department took 25 site photos at its inspections.
- Is The Alba Residences By Omniyat delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building The Alba Residences By Omniyat?
- The registered developer is Grandeur Beach Real Estate Development.
- Which bank holds the escrow account for The Alba Residences By Omniyat?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)