Oceana Hotel And Apartments construction progress

The register lists Oceana Hotel And Apartments in Palm Jumeirah as complete, with a registered completion date of February 2018. Its last site inspection on record was in January 2018. The developer is Seven Tides Limited.

100%

Built, at the site inspection of 3 January 2018

Construction complete

Registered completion date
February 2018
Construction started
April 2015
First registered
April 2015
Developer
Seven Tides Limited
Community
Palm Jumeirah
Units
290
Escrow bank
Emirates NBD
Name in Arabic
فندق وشقق أوشينا
Project number
1644
Site inspections
7

Schedule

The register lists Oceana Hotel And Apartments as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 January 2018

97%+0.5 pts

  • Oceana Hotel And Apartments construction site, inspection photo 1, 3 January 2018
  • Oceana Hotel And Apartments construction site, inspection photo 2, 3 January 2018
  • Oceana Hotel And Apartments construction site, inspection photo 3, 3 January 2018
  • Oceana Hotel And Apartments construction site, inspection photo 4, 3 January 2018

23 November 2017

96%+1.2 pts

  • Oceana Hotel And Apartments construction site, inspection photo 1, 23 November 2017
  • Oceana Hotel And Apartments construction site, inspection photo 2, 23 November 2017
  • Oceana Hotel And Apartments construction site, inspection photo 3, 23 November 2017
  • Oceana Hotel And Apartments construction site, inspection photo 4, 23 November 2017

5 July 2017

95%+4.1 pts

  • Oceana Hotel And Apartments construction site, inspection photo 1, 5 July 2017
  • Oceana Hotel And Apartments construction site, inspection photo 2, 5 July 2017
  • Oceana Hotel And Apartments construction site, inspection photo 3, 5 July 2017
  • Oceana Hotel And Apartments construction site, inspection photo 4, 5 July 2017

12 December 2016

91%+4.7 pts

  • Oceana Hotel And Apartments construction site, inspection photo 1, 12 December 2016
  • Oceana Hotel And Apartments construction site, inspection photo 2, 12 December 2016
  • Oceana Hotel And Apartments construction site, inspection photo 3, 12 December 2016
  • Oceana Hotel And Apartments construction site, inspection photo 4, 12 December 2016

31 August 2016

86%+10 pts

  • Oceana Hotel And Apartments construction site, inspection photo 1, 31 August 2016
  • Oceana Hotel And Apartments construction site, inspection photo 2, 31 August 2016
  • Oceana Hotel And Apartments construction site, inspection photo 3, 31 August 2016
  • Oceana Hotel And Apartments construction site, inspection photo 4, 31 August 2016

12 May 2016

76%+7.2 pts

  • Oceana Hotel And Apartments construction site, inspection photo 1, 12 May 2016
  • Oceana Hotel And Apartments construction site, inspection photo 2, 12 May 2016
  • Oceana Hotel And Apartments construction site, inspection photo 3, 12 May 2016
  • Oceana Hotel And Apartments construction site, inspection photo 4, 12 May 2016

1 October 2015

69%

  • Oceana Hotel And Apartments construction site, inspection photo 1, 1 October 2015
  • Oceana Hotel And Apartments construction site, inspection photo 2, 1 October 2015
  • Oceana Hotel And Apartments construction site, inspection photo 3, 1 October 2015
  • Oceana Hotel And Apartments construction site, inspection photo 4, 1 October 2015

All 62 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in Oceana Hotel And Apartments?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Oceana Hotel And Apartments handover date?
Construction of Oceana Hotel And Apartments is recorded as complete, with a registered completion date of February 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Oceana Hotel And Apartments?
Oceana Hotel And Apartments was 100% built at the site inspection on 3 January 2018. The site has been inspected 7 times since October 2015. The Land Department took 62 site photos at its inspections.
Is Oceana Hotel And Apartments delayed?
The register lists construction as complete.
Who is building Oceana Hotel And Apartments?
The registered developer is Seven Tides Limited.
Which bank holds the escrow account for Oceana Hotel And Apartments?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.