Oceana Hotel And Apartments construction photos
62 photos from 7 site inspections, newest first. The percentage is how much of Oceana Hotel And Apartments was built on the day of each visit.
3 January 201897% built
23 November 201796% built
5 July 201795% built
12 December 201691% built
31 August 201686% built
12 May 201676% built
1 October 201569% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.