Maison Margiela Residences construction progress
The registered completion date for Maison Margiela Residences in Palm Jumeirah is March 2028. At the last site inspection, in October 2026, it was 6.4% built. The developer is Alta Real Estate Development.
6.4%
Built, at the site inspection of 5 October 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- June 2047
- Construction started
- March 2025
- First registered
- October 2025
- Developer
- Alta Real Estate Development
- Community
- Palm Jumeirah
- Units
- 25
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- ميزون مارجيلا رزيدنسس
- Project number
- 3716
- Site inspections
- 5
Schedule
Between March 2026 and October 2026 the site added about 0.4 points a month. At that rate it would finish around June 2047, more than three months after its registered date of March 2028.
Site inspections
5 October 2026
6.4%+0.5 pts
2 July 2026
5.9%+1.8 pts
31 March 2026
4.0%+2.2 pts
22 September 2025
1.9%+0.5 pts
18 August 2025
1.4%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Alta Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Maison Margiela Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Maison Margiela Residences handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2047. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Maison Margiela Residences?
- Maison Margiela Residences was 6.4% built at the site inspection on 5 October 2026. The site has been inspected 5 times since August 2025. The Land Department took 23 site photos at its inspections.
- Is Maison Margiela Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Maison Margiela Residences?
- The registered developer is Alta Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Maison Margiela Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mr.C Residences DowntownAlso by Alta Real Estate Development. 81%, Due January 2027.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)