Skip to content

Mr.C Residences Downtown construction progress

The registered completion date for Mr.C Residences Downtown in Al Wasl is January 2027. At the last site inspection, in November 2026, it was 81% built. The developer is Alta Real Estate Development.

81%

Built, at the site inspection of 2 November 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
July 2027
Construction started
September 2021
First registered
November 2022
Developer
Alta Real Estate Development
Community
Al Wasl
Units
179
Escrow bank
Dubai Islamic Bank
Name in Arabic
مستر سي رزيدنسس داون تاون
Project number
2476
Site inspections
15

Schedule

Between December 2025 and November 2026 the site added about 2.2 points a month. At that rate it would finish around July 2027, more than three months after its registered date of January 2027.

0%25%50%75%100%202220242026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 November 2026

81%+7.3 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 2 November 2026
  • Mr.C Residences Downtown construction site, inspection photo 2, 2 November 2026
  • Mr.C Residences Downtown construction site, inspection photo 3, 2 November 2026
  • Mr.C Residences Downtown construction site, inspection photo 4, 2 November 2026

4 August 2026

73%+3.2 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 4 August 2026
  • Mr.C Residences Downtown construction site, inspection photo 2, 4 August 2026
  • Mr.C Residences Downtown construction site, inspection photo 3, 4 August 2026
  • Mr.C Residences Downtown construction site, inspection photo 4, 4 August 2026

29 April 2026

70%+7.0 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 29 April 2026
  • Mr.C Residences Downtown construction site, inspection photo 2, 29 April 2026
  • Mr.C Residences Downtown construction site, inspection photo 3, 29 April 2026
  • Mr.C Residences Downtown construction site, inspection photo 4, 29 April 2026

20 January 2026

63%+6.0 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 20 January 2026
  • Mr.C Residences Downtown construction site, inspection photo 2, 20 January 2026
  • Mr.C Residences Downtown construction site, inspection photo 3, 20 January 2026
  • Mr.C Residences Downtown construction site, inspection photo 4, 20 January 2026

17 December 2025

57%+7.0 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 17 December 2025
  • Mr.C Residences Downtown construction site, inspection photo 2, 17 December 2025
  • Mr.C Residences Downtown construction site, inspection photo 3, 17 December 2025
  • Mr.C Residences Downtown construction site, inspection photo 4, 17 December 2025

9 September 2025

50%+6.8 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 9 September 2025
  • Mr.C Residences Downtown construction site, inspection photo 2, 9 September 2025
  • Mr.C Residences Downtown construction site, inspection photo 3, 9 September 2025
  • Mr.C Residences Downtown construction site, inspection photo 4, 9 September 2025

15 May 2025

43%+2.0 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 15 May 2025
  • Mr.C Residences Downtown construction site, inspection photo 2, 15 May 2025
  • Mr.C Residences Downtown construction site, inspection photo 3, 15 May 2025
  • Mr.C Residences Downtown construction site, inspection photo 4, 15 May 2025

30 December 2024

41%+6.2 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 30 December 2024
  • Mr.C Residences Downtown construction site, inspection photo 2, 30 December 2024
  • Mr.C Residences Downtown construction site, inspection photo 3, 30 December 2024
  • Mr.C Residences Downtown construction site, inspection photo 4, 30 December 2024

20 August 2024

35%+5.1 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 20 August 2024
  • Mr.C Residences Downtown construction site, inspection photo 2, 20 August 2024
  • Mr.C Residences Downtown construction site, inspection photo 3, 20 August 2024
  • Mr.C Residences Downtown construction site, inspection photo 4, 20 August 2024

20 March 2024

30%+6.9 pts

  • Mr.C Residences Downtown construction site, inspection photo 1, 20 March 2024
  • Mr.C Residences Downtown construction site, inspection photo 2, 20 March 2024
  • Mr.C Residences Downtown construction site, inspection photo 3, 20 March 2024
  • Mr.C Residences Downtown construction site, inspection photo 4, 20 March 2024

All 131 site photos, by inspection date

Context

Alta Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Mr.C Residences Downtown?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Mr.C Residences Downtown handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Mr.C Residences Downtown?
Mr.C Residences Downtown was 81% built at the site inspection on 2 November 2026. The site has been inspected 15 times since November 2022. The Land Department took 131 site photos at its inspections.
Is Mr.C Residences Downtown delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Mr.C Residences Downtown?
The registered developer is Alta Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mr.C Residences Downtown?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.