Mr.C Residences Downtown construction progress
Mr.C Residences Downtown in Al Wasl is 73% built at the Land Department inspection of August 2026. Developer Alta Real Estate Development. Completion registered for January 2027.
73%
Built, at the Land Department site inspection of 4 August 2026
Running behind its date
- Completion date (Land Department)
- January 2027
- Finish at recent pace
- August 2027
- Construction started
- September 2021
- Registered with the Land Department
- November 2022
- Developer
- Alta Real Estate Development
- Community
- Al Wasl
- Units
- 169
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مستر سي رزيدنسس داون تاون
- Land Department project number
- 2476
- Land Department site inspections
- 14
Schedule
Between September 2025 and August 2026 the site added about 2.1 points a month. At that rate it would finish around August 2027, more than three months after the January 2027 date registered with the Land Department.
Site inspections
4 August 2026
73%+3.2 pts
29 April 2026
70%+7.0 pts
20 January 2026
63%+6.0 pts
17 December 2025
57%+7.0 pts
9 September 2025
50%+6.8 pts
15 May 2025
43%+2.0 pts
30 December 2024
41%+6.2 pts
20 August 2024
35%+5.1 pts
20 March 2024
30%+6.9 pts
23 October 2023
23%+3.1 pts
Context
Alta Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Mr.C Residences Downtown?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Mr.C Residences Downtown be completed?
- The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Mr.C Residences Downtown is built?
- 73%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 14 times since November 2022.
- Is Mr.C Residences Downtown delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Mr.C Residences Downtown?
- The registered developer is Alta Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Mr.C Residences Downtown?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)










.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)