Skip to content

Mr.C Residences Downtown construction progress

Mr.C Residences Downtown in Al Wasl is 73% built at the Land Department inspection of August 2026. Developer Alta Real Estate Development. Completion registered for January 2027.

73%

Built, at the Land Department site inspection of 4 August 2026

Running behind its date

Completion date (Land Department)
January 2027
Finish at recent pace
August 2027
Construction started
September 2021
Registered with the Land Department
November 2022
Developer
Alta Real Estate Development
Community
Al Wasl
Units
169
Escrow bank
Dubai Islamic Bank
Name in Arabic
مستر سي رزيدنسس داون تاون
Land Department project number
2476
Land Department site inspections
14

Schedule

Between September 2025 and August 2026 the site added about 2.1 points a month. At that rate it would finish around August 2027, more than three months after the January 2027 date registered with the Land Department.

0%25%50%75%100%202220242026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 August 2026

73%+3.2 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 4 August 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 4 August 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 4 August 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 4 August 2026

29 April 2026

70%+7.0 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 29 April 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 29 April 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 29 April 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 29 April 2026

20 January 2026

63%+6.0 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 20 January 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 20 January 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 20 January 2026
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 20 January 2026

17 December 2025

57%+7.0 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 17 December 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 17 December 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 17 December 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 17 December 2025

9 September 2025

50%+6.8 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 9 September 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 9 September 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 9 September 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 9 September 2025

15 May 2025

43%+2.0 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 15 May 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 15 May 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 15 May 2025
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 15 May 2025

30 December 2024

41%+6.2 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 30 December 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 30 December 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 30 December 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 30 December 2024

20 August 2024

35%+5.1 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 20 August 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 20 August 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 20 August 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 20 August 2024

20 March 2024

30%+6.9 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 20 March 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 20 March 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 20 March 2024
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 20 March 2024

23 October 2023

23%+3.1 pts

  • Mr.C Residences Downtown construction site, Land Department inspection photo 1, 23 October 2023
  • Mr.C Residences Downtown construction site, Land Department inspection photo 2, 23 October 2023
  • Mr.C Residences Downtown construction site, Land Department inspection photo 3, 23 October 2023
  • Mr.C Residences Downtown construction site, Land Department inspection photo 4, 23 October 2023

All 116 site photos, by inspection date

Context

Alta Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Mr.C Residences Downtown?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Mr.C Residences Downtown be completed?
The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mr.C Residences Downtown is built?
73%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 14 times since November 2022.
Is Mr.C Residences Downtown delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Mr.C Residences Downtown?
The registered developer is Alta Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Mr.C Residences Downtown?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.