Wellington Ocean By Ank Motiwala Developments construction progress

Wellington Ocean By Ank Motiwala Developments in Palm Deira is 26% built at the Land Department inspection of July 2026. Developer A N K Motiwala Real Estate Development. Completion registered for December 2027.

26%

Built, at the Land Department site inspection of 27 July 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
May 2029
Construction started
December 2024
Registered with the Land Department
February 2025
Developer
A N K Motiwala Real Estate Development
Community
Palm Deira
Units
49
Escrow bank
United Bank Limited
Name in Arabic
ويلينغتون أوشن من تطوير شركة إيه إن كيه ميتولى
Land Department project number
3452
Land Department site inspections
6

Schedule

Between October 2025 and July 2026 the site added about 2.2 points a month. At that rate it would finish around May 2029, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

26%+10 pts

  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 1, 27 July 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 2, 27 July 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 3, 27 July 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 4, 27 July 2026

22 April 2026

16%+5.5 pts

  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 1, 22 April 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 2, 22 April 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 3, 22 April 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 4, 22 April 2026

22 January 2026

10%+4.3 pts

  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 1, 22 January 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 2, 22 January 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 3, 22 January 2026
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 4, 22 January 2026

28 October 2025

6.2%+1.6 pts

  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 1, 28 October 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 2, 28 October 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 3, 28 October 2025

17 June 2025

4.6%+4.6 pts

  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 1, 17 June 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 2, 17 June 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 3, 17 June 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 4, 17 June 2025

22 January 2025

0%

  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 1, 22 January 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 2, 22 January 2025
  • Wellington Ocean By Ank Motiwala Developments construction site, Land Department inspection photo 3, 22 January 2025

All 29 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Own a unit in Wellington Ocean By Ank Motiwala Developments?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Wellington Ocean By Ank Motiwala Developments be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around May 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Wellington Ocean By Ank Motiwala Developments is built?
26%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 6 times since January 2025.
Is Wellington Ocean By Ank Motiwala Developments delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Wellington Ocean By Ank Motiwala Developments?
The registered developer is A N K Motiwala Real Estate Development.
Which bank holds the escrow account for Wellington Ocean By Ank Motiwala Developments?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.