Wellington Ocean By Ank Motiwala Developments construction photos

29 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Wellington Ocean By Ank Motiwala Developments was built on the day of each visit.

27 July 202626% built

22 April 202616% built

22 January 202610% built

28 October 20256.2% built

17 June 20254.6% built

22 January 20250% built

Back to Wellington Ocean By Ank Motiwala Developments construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.