Villa Del Divos Residences construction progress
The registered completion date for Villa Del Divos Residences in Palm Deira is June 2027. At the last site inspection, in October 2026, it was 52% built. The developer is Divo Home Real Estate Development.
52%
Built, at the site inspection of 1 October 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- October 2027
- Construction started
- December 2024
- First registered
- February 2025
- Developer
- Divo Home Real Estate Development
- Community
- Palm Deira
- Units
- 106
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- فيلا ديل ديفوس ريزدنسز
- Project number
- 3489
- Site inspections
- 7
Schedule
Between October 2025 and October 2026 the site added about 3.9 points a month. At that rate it would finish around October 2027, more than three months after its registered date of June 2027.
Site inspections
1 October 2026
52%+17 pts
24 June 2026
35%+17 pts
25 March 2026
18%+5.3 pts
18 February 2026
12%+7.2 pts
6 October 2025
5.3%+5.3 pts
21 May 2025
0%
13 January 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Divo Home Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Villa Del Divos Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Villa Del Divos Residences handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Villa Del Divos Residences?
- Villa Del Divos Residences was 52% built at the site inspection on 1 October 2026. The site has been inspected 7 times since January 2025. The Land Department took 37 site photos at its inspections.
- Is Villa Del Divos Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Villa Del Divos Residences?
- The registered developer is Divo Home Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Villa Del Divos Residences?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Villa Del Brunello ResidencesAlso by Divo Home Real Estate Development. 2.2%, Due November 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)






.jpeg&w=3840&q=75)