Villa Del Divos Residences construction progress

The registered completion date for Villa Del Divos Residences in Palm Deira is June 2027. At the last site inspection, in October 2026, it was 52% built. The developer is Divo Home Real Estate Development.

52%

Built, at the site inspection of 1 October 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
October 2027
Construction started
December 2024
First registered
February 2025
Developer
Divo Home Real Estate Development
Community
Palm Deira
Units
106
Escrow bank
Bank of Sharjah
Name in Arabic
فيلا ديل ديفوس ريزدنسز
Project number
3489
Site inspections
7

Schedule

Between October 2025 and October 2026 the site added about 3.9 points a month. At that rate it would finish around October 2027, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2026

52%+17 pts

  • Villa Del Divos Residences construction site, inspection photo 1, 1 October 2026
  • Villa Del Divos Residences construction site, inspection photo 2, 1 October 2026
  • Villa Del Divos Residences construction site, inspection photo 3, 1 October 2026
  • Villa Del Divos Residences construction site, inspection photo 4, 1 October 2026

24 June 2026

35%+17 pts

  • Villa Del Divos Residences construction site, inspection photo 1, 24 June 2026
  • Villa Del Divos Residences construction site, inspection photo 2, 24 June 2026
  • Villa Del Divos Residences construction site, inspection photo 3, 24 June 2026
  • Villa Del Divos Residences construction site, inspection photo 4, 24 June 2026

25 March 2026

18%+5.3 pts

  • Villa Del Divos Residences construction site, inspection photo 1, 25 March 2026
  • Villa Del Divos Residences construction site, inspection photo 2, 25 March 2026
  • Villa Del Divos Residences construction site, inspection photo 3, 25 March 2026
  • Villa Del Divos Residences construction site, inspection photo 4, 25 March 2026

18 February 2026

12%+7.2 pts

  • Villa Del Divos Residences construction site, inspection photo 1, 18 February 2026
  • Villa Del Divos Residences construction site, inspection photo 2, 18 February 2026
  • Villa Del Divos Residences construction site, inspection photo 3, 18 February 2026
  • Villa Del Divos Residences construction site, inspection photo 4, 18 February 2026

6 October 2025

5.3%+5.3 pts

  • Villa Del Divos Residences construction site, inspection photo 1, 6 October 2025
  • Villa Del Divos Residences construction site, inspection photo 2, 6 October 2025
  • Villa Del Divos Residences construction site, inspection photo 3, 6 October 2025

21 May 2025

0%

  • Villa Del Divos Residences construction site, inspection photo 1, 21 May 2025
  • Villa Del Divos Residences construction site, inspection photo 2, 21 May 2025

13 January 2025

0%

  • Villa Del Divos Residences construction site, inspection photo 1, 13 January 2025
  • Villa Del Divos Residences construction site, inspection photo 2, 13 January 2025

All 37 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Divo Home Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Villa Del Divos Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Villa Del Divos Residences handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Villa Del Divos Residences?
Villa Del Divos Residences was 52% built at the site inspection on 1 October 2026. The site has been inspected 7 times since January 2025. The Land Department took 37 site photos at its inspections.
Is Villa Del Divos Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Villa Del Divos Residences?
The registered developer is Divo Home Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Villa Del Divos Residences?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.