Villa Del Divos Residences construction progress
Villa Del Divos Residences in Palm Deira is 52% built at the Land Department inspection of October 2026. Developer Divo Home Real Estate Development. Completion registered for June 2027.
52%
Built, at the Land Department site inspection of 1 October 2026
Running behind its date
- Completion date (Land Department)
- June 2027
- Finish at recent pace
- October 2027
- Construction started
- December 2024
- Registered with the Land Department
- February 2025
- Developer
- Divo Home Real Estate Development
- Community
- Palm Deira
- Units
- 106
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- فيلا ديل ديفوس ريزدنسز
- Land Department project number
- 3489
- Land Department site inspections
- 7
Schedule
Between October 2025 and October 2026 the site added about 3.9 points a month. At that rate it would finish around October 2027, more than three months after the June 2027 date registered with the Land Department.
Site inspections
1 October 2026
52%+17 pts
24 June 2026
35%+17 pts
25 March 2026
18%+5.3 pts
18 February 2026
12%+7.2 pts
6 October 2025
5.3%+5.3 pts
21 May 2025
0%
13 January 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Divo Home Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Villa Del Divos Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Villa Del Divos Residences be completed?
- The completion date registered with the Dubai Land Department is June 2027. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Villa Del Divos Residences is built?
- 52%, measured at the Land Department site inspection on 1 October 2026. The Land Department engineers have inspected the site 7 times since January 2025.
- Is Villa Del Divos Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Villa Del Divos Residences?
- The registered developer is Divo Home Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Villa Del Divos Residences?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Villa Del Brunello ResidencesAlso by Divo Home Real Estate Development. 2.2%, Due November 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)