Villa Del Brunello Residences construction progress

The registered completion date for Villa Del Brunello Residences in Palm Deira is November 2027. At the last site inspection, in June 2026, it was 2.2% built. The developer is Divo Home Real Estate Development.

2.2%

Built, at the site inspection of 16 June 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
February 2064
Construction started
November 2025
First registered
October 2025
Developer
Divo Home Real Estate Development
Community
Palm Deira
Units
69
Escrow bank
Bank of Sharjah
Name in Arabic
فيلا ديل برونيلو رزيدينسيز
Project number
4011
Site inspections
2

Schedule

Between August 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around February 2064, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 June 2026

2.2%+2.2 pts

  • Villa Del Brunello Residences construction site, inspection photo 1, 16 June 2026
  • Villa Del Brunello Residences construction site, inspection photo 2, 16 June 2026
  • Villa Del Brunello Residences construction site, inspection photo 3, 16 June 2026
  • Villa Del Brunello Residences construction site, inspection photo 4, 16 June 2026

6 August 2025

0%

  • Villa Del Brunello Residences construction site, inspection photo 1, 6 August 2025
  • Villa Del Brunello Residences construction site, inspection photo 2, 6 August 2025

All 7 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Divo Home Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Villa Del Brunello Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Villa Del Brunello Residences handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2064. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Villa Del Brunello Residences?
Villa Del Brunello Residences was 2.2% built at the site inspection on 16 June 2026. The site has been inspected 2 times since August 2025. The Land Department took 7 site photos at its inspections.
Is Villa Del Brunello Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Villa Del Brunello Residences?
The registered developer is Divo Home Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Villa Del Brunello Residences?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.