Villa Del Brunello Residences construction progress
Villa Del Brunello Residences in Palm Deira is 2.2% built at the Land Department inspection of June 2026. Developer Divo Home Real Estate Development. Completion registered for November 2027.
2.2%
Built, at the Land Department site inspection of 16 June 2026
Running behind its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- February 2064
- Construction started
- November 2025
- Registered with the Land Department
- October 2025
- Developer
- Divo Home Real Estate Development
- Community
- Palm Deira
- Units
- 69
- Escrow bank
- Bank of Sharjah
- Name in Arabic
- فيلا ديل برونيلو رزيدينسيز
- Land Department project number
- 4011
- Land Department site inspections
- 2
Schedule
Between August 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around February 2064, more than three months after the November 2027 date registered with the Land Department.
Site inspections
16 June 2026
2.2%+2.2 pts
6 August 2025
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Divo Home Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Villa Del Brunello Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Villa Del Brunello Residences be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around February 2064. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Villa Del Brunello Residences is built?
- 2.2%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 2 times since August 2025.
- Is Villa Del Brunello Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Villa Del Brunello Residences?
- The registered developer is Divo Home Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Villa Del Brunello Residences?
- Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Villa Del Divos ResidencesAlso by Divo Home Real Estate Development. 52%, Due June 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.


.jpeg&w=3840&q=75)