Villa Del Brunello Residences construction progress

Villa Del Brunello Residences in Palm Deira is 2.2% built at the Land Department inspection of June 2026. Developer Divo Home Real Estate Development. Completion registered for November 2027.

2.2%

Built, at the Land Department site inspection of 16 June 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
February 2064
Construction started
November 2025
Registered with the Land Department
October 2025
Developer
Divo Home Real Estate Development
Community
Palm Deira
Units
69
Escrow bank
Bank of Sharjah
Name in Arabic
فيلا ديل برونيلو رزيدينسيز
Land Department project number
4011
Land Department site inspections
2

Schedule

Between August 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around February 2064, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 June 2026

2.2%+2.2 pts

  • Villa Del Brunello Residences construction site, Land Department inspection photo 1, 16 June 2026
  • Villa Del Brunello Residences construction site, Land Department inspection photo 2, 16 June 2026
  • Villa Del Brunello Residences construction site, Land Department inspection photo 3, 16 June 2026
  • Villa Del Brunello Residences construction site, Land Department inspection photo 4, 16 June 2026

6 August 2025

0%

  • Villa Del Brunello Residences construction site, Land Department inspection photo 1, 6 August 2025
  • Villa Del Brunello Residences construction site, Land Department inspection photo 2, 6 August 2025

All 7 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Divo Home Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Villa Del Brunello Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Villa Del Brunello Residences be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around February 2064. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Villa Del Brunello Residences is built?
2.2%, measured at the Land Department site inspection on 16 June 2026. The Land Department engineers have inspected the site 2 times since August 2025.
Is Villa Del Brunello Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Villa Del Brunello Residences?
The registered developer is Divo Home Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Villa Del Brunello Residences?
Bank of Sharjah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.