Meriden Beach By Green Horizon construction progress

Meriden Beach By Green Horizon in Palm Deira is 1.4% built at the Land Department inspection of April 2026. Developer Green Horizon Real Estate Development. Completion registered for December 2027.

1.4%

Built, at the Land Department site inspection of 29 April 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
October 2074
Construction started
December 2025
Registered with the Land Department
November 2025
Developer
Green Horizon Real Estate Development
Community
Palm Deira
Units
65
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ميريدين بيتش باي جرين هوريزون
Land Department project number
4010
Land Department site inspections
2

Schedule

Between August 2025 and April 2026 the site added about 0.2 points a month. At that rate it would finish around October 2074, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 April 2026

1.4%+1.4 pts

  • Meriden Beach By Green Horizon construction site, Land Department inspection photo 1, 29 April 2026
  • Meriden Beach By Green Horizon construction site, Land Department inspection photo 2, 29 April 2026
  • Meriden Beach By Green Horizon construction site, Land Department inspection photo 3, 29 April 2026
  • Meriden Beach By Green Horizon construction site, Land Department inspection photo 4, 29 April 2026

26 August 2025

0%

  • Meriden Beach By Green Horizon construction site, Land Department inspection photo 1, 26 August 2025
  • Meriden Beach By Green Horizon construction site, Land Department inspection photo 2, 26 August 2025

All 8 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Meriden Beach By Green Horizon is behind that average.

Own a unit in Meriden Beach By Green Horizon?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Meriden Beach By Green Horizon be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around October 2074. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Meriden Beach By Green Horizon is built?
1.4%, measured at the Land Department site inspection on 29 April 2026. The Land Department engineers have inspected the site 2 times since August 2025.
Is Meriden Beach By Green Horizon delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Meriden Beach By Green Horizon?
The registered developer is Green Horizon Real Estate Development.
Which bank holds the escrow account for Meriden Beach By Green Horizon?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.