Luxury Canal Residences construction progress

Luxury Canal Residences in Palm Deira is 18% built at the Land Department inspection of June 2026. Developer Prestige Harbour Real Estate Development. Completion registered for November 2027.

18%

Built, at the Land Department site inspection of 30 June 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
July 2030
Construction started
July 2025
Registered with the Land Department
March 2025
Developer
Prestige Harbour Real Estate Development
Community
Palm Deira
Units
73
Escrow bank
Emirates Islamic Bank
Name in Arabic
لكشري كانال ريزيدنسز
Land Department project number
3568
Land Department site inspections
4

Schedule

Between November 2025 and June 2026 the site added about 1.7 points a month. At that rate it would finish around July 2030, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 June 2026

18%+8.2 pts

  • Luxury Canal Residences construction site, Land Department inspection photo 1, 30 June 2026
  • Luxury Canal Residences construction site, Land Department inspection photo 2, 30 June 2026
  • Luxury Canal Residences construction site, Land Department inspection photo 3, 30 June 2026
  • Luxury Canal Residences construction site, Land Department inspection photo 4, 30 June 2026

23 March 2026

9.5%+4.1 pts

  • Luxury Canal Residences construction site, Land Department inspection photo 1, 23 March 2026
  • Luxury Canal Residences construction site, Land Department inspection photo 2, 23 March 2026
  • Luxury Canal Residences construction site, Land Department inspection photo 3, 23 March 2026
  • Luxury Canal Residences construction site, Land Department inspection photo 4, 23 March 2026

20 November 2025

5.4%+5.4 pts

  • Luxury Canal Residences construction site, Land Department inspection photo 1, 20 November 2025
  • Luxury Canal Residences construction site, Land Department inspection photo 2, 20 November 2025
  • Luxury Canal Residences construction site, Land Department inspection photo 3, 20 November 2025
  • Luxury Canal Residences construction site, Land Department inspection photo 4, 20 November 2025

18 February 2025

0%

  • Luxury Canal Residences construction site, Land Department inspection photo 1, 18 February 2025
  • Luxury Canal Residences construction site, Land Department inspection photo 2, 18 February 2025

All 19 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Prestige Harbour Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Luxury Canal Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Luxury Canal Residences be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around July 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Luxury Canal Residences is built?
18%, measured at the Land Department site inspection on 30 June 2026. The Land Department engineers have inspected the site 4 times since February 2025.
Is Luxury Canal Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Luxury Canal Residences?
The registered developer is Prestige Harbour Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Luxury Canal Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.