Coastal Haven By Prestige Harbour Real Estate Development construction progress

The registered completion date for Coastal Haven By Prestige Harbour Real Estate Development in Palm Deira is November 2027. At the last site inspection, in October 2026, it was 33% built. The developer is Prestige Harbour Real Estate Development.

33%

Built, at the site inspection of 8 October 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
December 2028
Construction started
July 2025
First registered
February 2025
Developer
Prestige Harbour Real Estate Development
Community
Palm Deira
Units
73
Escrow bank
Emirates Islamic Bank
Name in Arabic
كوستال هافين من بريستيج هاربور للتطوير العقاري
Project number
3544
Site inspections
5

Schedule

Between November 2025 and October 2026 the site added about 2.5 points a month. At that rate it would finish around December 2028, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 October 2026

33%+9.9 pts

  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 1, 8 October 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 2, 8 October 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 3, 8 October 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 4, 8 October 2026

30 June 2026

23%+11 pts

  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 1, 30 June 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 2, 30 June 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 3, 30 June 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 4, 30 June 2026

23 March 2026

12%+5.5 pts

  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 1, 23 March 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 2, 23 March 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 3, 23 March 2026
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 4, 23 March 2026

20 November 2025

6.2%+6.2 pts

  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 1, 20 November 2025
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 2, 20 November 2025
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 3, 20 November 2025
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 4, 20 November 2025

4 February 2025

0%

  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 1, 4 February 2025
  • Coastal Haven By Prestige Harbour Real Estate Development construction site, inspection photo 2, 4 February 2025

All 26 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 25% built on average.

Prestige Harbour Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Coastal Haven By Prestige Harbour Real Estate Development?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Coastal Haven By Prestige Harbour Real Estate Development handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Coastal Haven By Prestige Harbour Real Estate Development?
Coastal Haven By Prestige Harbour Real Estate Development was 33% built at the site inspection on 8 October 2026. The site has been inspected 5 times since February 2025. The Land Department took 26 site photos at its inspections.
Is Coastal Haven By Prestige Harbour Real Estate Development delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Coastal Haven By Prestige Harbour Real Estate Development?
The registered developer is Prestige Harbour Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Coastal Haven By Prestige Harbour Real Estate Development?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.