Haven Bay Residences construction progress

Haven Bay Residences in Palm Deira was registered to complete in June 2026 and is still under construction. At the last site inspection, in August 2026, it was 83% built. The developer is Metac Properties.

83%

Built, at the site inspection of 6 August 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
November 2026
Construction started
July 2024
First registered
September 2024
Developer
Metac Properties
Community
Palm Deira
Units
64
Escrow bank
Commercial Bank of Dubai
Name in Arabic
هايفين باي ريزيدنسز
Project number
3101
Site inspections
7

Schedule

Haven Bay Residences was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 5.3 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 August 2026

83%+16 pts

  • Haven Bay Residences construction site, inspection photo 1, 6 August 2026
  • Haven Bay Residences construction site, inspection photo 2, 6 August 2026
  • Haven Bay Residences construction site, inspection photo 3, 6 August 2026
  • Haven Bay Residences construction site, inspection photo 4, 6 August 2026

7 May 2026

67%+25 pts

  • Haven Bay Residences construction site, inspection photo 1, 7 May 2026
  • Haven Bay Residences construction site, inspection photo 2, 7 May 2026
  • Haven Bay Residences construction site, inspection photo 3, 7 May 2026
  • Haven Bay Residences construction site, inspection photo 4, 7 May 2026

8 December 2025

41%+20 pts

  • Haven Bay Residences construction site, inspection photo 1, 8 December 2025
  • Haven Bay Residences construction site, inspection photo 2, 8 December 2025
  • Haven Bay Residences construction site, inspection photo 3, 8 December 2025
  • Haven Bay Residences construction site, inspection photo 4, 8 December 2025

22 July 2025

21%+15 pts

  • Haven Bay Residences construction site, inspection photo 1, 22 July 2025
  • Haven Bay Residences construction site, inspection photo 2, 22 July 2025
  • Haven Bay Residences construction site, inspection photo 3, 22 July 2025
  • Haven Bay Residences construction site, inspection photo 4, 22 July 2025

11 March 2025

6.4%+4.8 pts

  • Haven Bay Residences construction site, inspection photo 1, 11 March 2025
  • Haven Bay Residences construction site, inspection photo 2, 11 March 2025
  • Haven Bay Residences construction site, inspection photo 3, 11 March 2025
  • Haven Bay Residences construction site, inspection photo 4, 11 March 2025

20 November 2024

1.6%+1.6 pts

  • Haven Bay Residences construction site, inspection photo 1, 20 November 2024
  • Haven Bay Residences construction site, inspection photo 2, 20 November 2024
  • Haven Bay Residences construction site, inspection photo 3, 20 November 2024
  • Haven Bay Residences construction site, inspection photo 4, 20 November 2024

4 July 2024

0%

  • Haven Bay Residences construction site, inspection photo 1, 4 July 2024
  • Haven Bay Residences construction site, inspection photo 2, 4 July 2024

All 44 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Haven Bay Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Haven Bay Residences handover date?
The registered completion date was June 2026, and the register still lists Haven Bay Residences as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Haven Bay Residences?
Haven Bay Residences was 83% built at the site inspection on 6 August 2026. The site has been inspected 7 times since July 2024. The Land Department took 44 site photos at its inspections.
Is Haven Bay Residences delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Haven Bay Residences?
The registered developer is Metac Properties.
Which bank holds the escrow account for Haven Bay Residences?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.