Haven Bay Residences construction photos
44 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Haven Bay Residences was built on the day of each visit.
6 August 202683% built
7 May 202667% built
8 December 202541% built
22 July 202521% built
11 March 20256.4% built
20 November 20241.6% built
4 July 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.