Dreamlife Residences construction progress

The registered completion date for Dreamlife Residences in Palm Deira is January 2027. At the last site inspection, in September 2026, it was 31% built. The developer is Nova Power Real Estate.

31%

Built, at the site inspection of 3 September 2026

Running behind its date

Registered completion date
January 2027
Finish at recent pace
February 2029
Construction started
January 2025
First registered
June 2025
Developer
Nova Power Real Estate
Community
Palm Deira
Units
103
Escrow bank
First Abu Dhabi Bank
Name in Arabic
دريم لايف ريزيدنسيز
Project number
3683
Site inspections
3

Schedule

Between April 2026 and September 2026 the site added about 2.3 points a month. At that rate it would finish around February 2029, more than three months after its registered date of January 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 September 2026

31%+9.7 pts

  • Dreamlife Residences construction site, inspection photo 1, 3 September 2026
  • Dreamlife Residences construction site, inspection photo 2, 3 September 2026
  • Dreamlife Residences construction site, inspection photo 3, 3 September 2026
  • Dreamlife Residences construction site, inspection photo 4, 3 September 2026

29 April 2026

21%+21 pts

  • Dreamlife Residences construction site, inspection photo 1, 29 April 2026
  • Dreamlife Residences construction site, inspection photo 2, 29 April 2026
  • Dreamlife Residences construction site, inspection photo 3, 29 April 2026
  • Dreamlife Residences construction site, inspection photo 4, 29 April 2026

23 April 2025

0%

  • Dreamlife Residences construction site, inspection photo 1, 23 April 2025
  • Dreamlife Residences construction site, inspection photo 2, 23 April 2025
  • Dreamlife Residences construction site, inspection photo 3, 23 April 2025

All 19 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Dreamlife Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Dreamlife Residences handover date?
The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Dreamlife Residences?
Dreamlife Residences was 31% built at the site inspection on 3 September 2026. The site has been inspected 3 times since April 2025. The Land Department took 19 site photos at its inspections.
Is Dreamlife Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
Who is building Dreamlife Residences?
The registered developer is Nova Power Real Estate.
Which bank holds the escrow account for Dreamlife Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.