Capital Horizon Terraces construction progress

Capital Horizon Terraces in Palm Deira was registered to complete in October 2026 and is still under construction. At the last site inspection, in September 2026, it was 4.4% built. The developer is Capital International Real Estate Developer.

4.4%

Built, at the site inspection of 15 September 2026

1 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
April 2065
Construction started
November 2024
First registered
January 2025
Developer
Capital International Real Estate Developer
Community
Palm Deira
Units
63
Escrow bank
Mashreq Bank
Name in Arabic
كابيتال هورايزون تيراسيس
Project number
3401
Site inspections
2

Schedule

Capital Horizon Terraces was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around April 2065.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 September 2026

4.4%+4.4 pts

  • Capital Horizon Terraces construction site, inspection photo 1, 15 September 2026
  • Capital Horizon Terraces construction site, inspection photo 2, 15 September 2026
  • Capital Horizon Terraces construction site, inspection photo 3, 15 September 2026
  • Capital Horizon Terraces construction site, inspection photo 4, 15 September 2026

4 December 2024

0%

  • Capital Horizon Terraces construction site, inspection photo 1, 4 December 2024
  • Capital Horizon Terraces construction site, inspection photo 2, 4 December 2024

All 8 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Own a unit in Capital Horizon Terraces?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Capital Horizon Terraces handover date?
The registered completion date was October 2026, and the register still lists Capital Horizon Terraces as under construction. At the pace of its recent inspections the site would reach 100% around April 2065. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Capital Horizon Terraces?
Capital Horizon Terraces was 4.4% built at the site inspection on 15 September 2026. The site has been inspected 2 times since December 2024. The Land Department took 8 site photos at its inspections.
Is Capital Horizon Terraces delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Capital Horizon Terraces?
The registered developer is Capital International Real Estate Developer.
Which bank holds the escrow account for Capital Horizon Terraces?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.