Beach Walk Grand By Imtiaz construction progress

Beach Walk Grand By Imtiaz in Palm Deira is 53% built at the Land Department inspection of August 2026. Developer Imtiaz Bwg Real Estate Development. Completion registered for December 2026.

53%

Built, at the Land Department site inspection of 10 August 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
July 2027
Construction started
December 2024
Registered with the Land Department
December 2024
Developer
Imtiaz Bwg Real Estate Development
Community
Palm Deira
Units
112
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيتش ووك جراند من امتياز
Land Department project number
3367
Land Department site inspections
7

Schedule

Between November 2025 and August 2026 the site added about 4.3 points a month. At that rate it would finish around July 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 August 2026

53%+8.6 pts

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 10 August 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 10 August 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 3, 10 August 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 4, 10 August 2026

1 June 2026

45%+16 pts

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 1 June 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 1 June 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 3, 1 June 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 4, 1 June 2026

20 February 2026

29%+15 pts

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 20 February 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 20 February 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 3, 20 February 2026
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 4, 20 February 2026

7 November 2025

14%+7.8 pts

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 7 November 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 7 November 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 3, 7 November 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 4, 7 November 2025

4 August 2025

6.1%+5.9 pts

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 4 August 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 4 August 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 3, 4 August 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 4, 4 August 2025

23 April 2025

0.2%+0.2 pts

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 23 April 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 23 April 2025
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 3, 23 April 2025

4 November 2024

0%

  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 1, 4 November 2024
  • Beach Walk Grand By Imtiaz construction site, Land Department inspection photo 2, 4 November 2024

All 43 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average. Beach Walk Grand By Imtiaz is ahead of that average.

Own a unit in Beach Walk Grand By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Beach Walk Grand By Imtiaz be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Beach Walk Grand By Imtiaz is built?
53%, measured at the Land Department site inspection on 10 August 2026. The Land Department engineers have inspected the site 7 times since November 2024.
Is Beach Walk Grand By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Beach Walk Grand By Imtiaz?
The registered developer is Imtiaz Bwg Real Estate Development.
Which bank holds the escrow account for Beach Walk Grand By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.