Beach Walk Grand By Imtiaz construction photos

54 photos from 8 site inspections, newest first. The percentage is how much of Beach Walk Grand By Imtiaz was built on the day of each visit.

9 November 202668% built

10 August 202653% built

1 June 202645% built

20 February 202629% built

7 November 202514% built

4 August 20256.1% built

23 April 20250.2% built

4 November 20240% built

Back to Beach Walk Grand By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.