Skip to content

Bay Grove Residences, Dubai Islands construction progress

Bay Grove Residences, Dubai Islands in Palm Deira is 6.6% built at the Land Department inspection of July 2026. Developer Dubai Islands. Completion registered for March 2028.

6.6%

Built, at the Land Department site inspection of 21 July 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
November 2034
Construction started
December 2024
Registered with the Land Department
October 2024
Developer
Dubai Islands
Community
Palm Deira
Units
296
Escrow bank
First Abu Dhabi Bank
Name in Arabic
باي غروف ريزيدنسز , جزر دبي
Land Department project number
3293
Land Department site inspections
5

Schedule

Between January 2026 and July 2026 the site added about 0.9 points a month. At that rate it would finish around November 2034, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

21 July 2026

6.6%+2.9 pts

  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 1, 21 July 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 2, 21 July 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 3, 21 July 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 4, 21 July 2026

28 April 2026

3.7%+2.5 pts

  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 1, 28 April 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 2, 28 April 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 3, 28 April 2026

26 January 2026

1.2%+1.2 pts

  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 1, 26 January 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 2, 26 January 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 3, 26 January 2026
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 4, 26 January 2026

17 June 2025

0%

  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 1, 17 June 2025
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 2, 17 June 2025
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 3, 17 June 2025

19 September 2024

0%

  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 1, 19 September 2024
  • Bay Grove Residences, Dubai Islands construction site, Land Department inspection photo 2, 19 September 2024

All 21 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Dubai Islands has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Bay Grove Residences, Dubai Islands?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Bay Grove Residences, Dubai Islands be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around November 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Bay Grove Residences, Dubai Islands is built?
6.6%, measured at the Land Department site inspection on 21 July 2026. The Land Department engineers have inspected the site 5 times since September 2024.
Is Bay Grove Residences, Dubai Islands delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Bay Grove Residences, Dubai Islands?
The registered developer is Dubai Islands. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Bay Grove Residences, Dubai Islands?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.