Ayamore Residence construction progress
The registered completion date for Ayamore Residence in Palm Deira is March 2027. At the last site inspection, in July 2026, it was 68% built. The developer is Ayat Real Estate Development.
68%
Built, at the site inspection of 8 July 2026
On pace for its date
- Registered completion date
- March 2027
- Finish at recent pace
- April 2027
- Construction started
- November 2024
- First registered
- February 2025
- Developer
- Ayat Real Estate Development
- Community
- Palm Deira
- Units
- 94
- Escrow bank
- Emirates NBD
- Name in Arabic
- آياموري ريزيدنس
- Project number
- 3561
- Site inspections
- 4
Schedule
Since September 2025 Ayamore Residence has added about 3.4 points a month. That puts 100% around April 2027, within three months of its registered completion date of March 2027.
Site inspections
8 July 2026
68%+14 pts
26 February 2026
54%+20 pts
11 September 2025
34%+14 pts
18 February 2025
20%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Ayat Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ayamore Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ayamore Residence handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ayamore Residence?
- Ayamore Residence was 68% built at the site inspection on 8 July 2026. The site has been inspected 4 times since February 2025. The Land Department took 30 site photos at its inspections.
- Is Ayamore Residence delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
- Who is building Ayamore Residence?
- The registered developer is Ayat Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Ayamore Residence?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ayami Residence, By Ayat DevelopmentAlso by Ayat Real Estate Development. 0.1%, Due December 2028.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)