Ayamore Residence construction photos
30 photos taken by Dubai Land Department engineers at 4 site inspections, newest first. The percentage is how much of Ayamore Residence was built on the day of each visit.
8 July 202668% built
26 February 202654% built
11 September 202534% built
18 February 202520% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.