Allegro Residences construction progress

Allegro Residences in Palm Deira was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 84% built. The developer is Mill Hill Riviera Development.

84%

Built, at the site inspection of 5 October 2026

8 months past its registered completion date

Registered completion date
April 2026
Finish at recent pace
January 2027
Construction started
October 2024
First registered
December 2024
Developer
Mill Hill Riviera Development
Community
Palm Deira
Units
60
Escrow bank
First Abu Dhabi Bank
Name in Arabic
اليجرو ريزيدنسز
Project number
3404
Site inspections
8

Schedule

Allegro Residences was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

84%+7.0 pts

  • Allegro Residences construction site, inspection photo 1, 5 October 2026
  • Allegro Residences construction site, inspection photo 2, 5 October 2026
  • Allegro Residences construction site, inspection photo 3, 5 October 2026
  • Allegro Residences construction site, inspection photo 4, 5 October 2026

4 August 2026

77%+7.5 pts

  • Allegro Residences construction site, inspection photo 1, 4 August 2026
  • Allegro Residences construction site, inspection photo 2, 4 August 2026
  • Allegro Residences construction site, inspection photo 3, 4 August 2026
  • Allegro Residences construction site, inspection photo 4, 4 August 2026

7 May 2026

70%+14 pts

  • Allegro Residences construction site, inspection photo 1, 7 May 2026
  • Allegro Residences construction site, inspection photo 2, 7 May 2026
  • Allegro Residences construction site, inspection photo 3, 7 May 2026
  • Allegro Residences construction site, inspection photo 4, 7 May 2026

5 March 2026

56%+22 pts

  • Allegro Residences construction site, inspection photo 1, 5 March 2026
  • Allegro Residences construction site, inspection photo 2, 5 March 2026
  • Allegro Residences construction site, inspection photo 3, 5 March 2026
  • Allegro Residences construction site, inspection photo 4, 5 March 2026

26 November 2025

35%+17 pts

  • Allegro Residences construction site, inspection photo 1, 26 November 2025
  • Allegro Residences construction site, inspection photo 2, 26 November 2025
  • Allegro Residences construction site, inspection photo 3, 26 November 2025
  • Allegro Residences construction site, inspection photo 4, 26 November 2025

4 August 2025

18%+12 pts

  • Allegro Residences construction site, inspection photo 1, 4 August 2025
  • Allegro Residences construction site, inspection photo 2, 4 August 2025
  • Allegro Residences construction site, inspection photo 3, 4 August 2025
  • Allegro Residences construction site, inspection photo 4, 4 August 2025

17 March 2025

6.1%+6.1 pts

  • Allegro Residences construction site, inspection photo 1, 17 March 2025
  • Allegro Residences construction site, inspection photo 2, 17 March 2025
  • Allegro Residences construction site, inspection photo 3, 17 March 2025
  • Allegro Residences construction site, inspection photo 4, 17 March 2025

29 November 2024

0%

  • Allegro Residences construction site, inspection photo 1, 29 November 2024
  • Allegro Residences construction site, inspection photo 2, 29 November 2024

All 62 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Mill Hill Riviera Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Allegro Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Allegro Residences handover date?
The registered completion date was April 2026, and the register still lists Allegro Residences as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Allegro Residences?
Allegro Residences was 84% built at the site inspection on 5 October 2026. The site has been inspected 8 times since November 2024. The Land Department took 62 site photos at its inspections.
Is Allegro Residences delayed?
Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
Who is building Allegro Residences?
The registered developer is Mill Hill Riviera Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Allegro Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.