Allegro Residences construction progress
Allegro Residences in Palm Deira was registered to complete in April 2026 and is still under construction. At the last site inspection, in October 2026, it was 84% built. The developer is Mill Hill Riviera Development.
84%
Built, at the site inspection of 5 October 2026
8 months past its registered completion date
- Registered completion date
- April 2026
- Finish at recent pace
- January 2027
- Construction started
- October 2024
- First registered
- December 2024
- Developer
- Mill Hill Riviera Development
- Community
- Palm Deira
- Units
- 60
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- اليجرو ريزيدنسز
- Project number
- 3404
- Site inspections
- 8
Schedule
Allegro Residences was registered to complete in April 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
5 October 2026
84%+7.0 pts
4 August 2026
77%+7.5 pts
7 May 2026
70%+14 pts
5 March 2026
56%+22 pts
26 November 2025
35%+17 pts
4 August 2025
18%+12 pts
17 March 2025
6.1%+6.1 pts
29 November 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Mill Hill Riviera Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Allegro Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Allegro Residences handover date?
- The registered completion date was April 2026, and the register still lists Allegro Residences as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Allegro Residences?
- Allegro Residences was 84% built at the site inspection on 5 October 2026. The site has been inspected 8 times since November 2024. The Land Department took 62 site photos at its inspections.
- Is Allegro Residences delayed?
- Yes. Its registered completion date of April 2026 has passed and the project is still listed as under construction.
- Who is building Allegro Residences?
- The registered developer is Mill Hill Riviera Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Allegro Residences?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Allegro Park By Mill Hill Riviera DevelopmentAlso by Mill Hill Riviera Development. 4.2%, Due April 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.









.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)












.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)