Allegro Residences construction progress

Allegro Residences in Palm Deira is 77% built at the Land Department inspection of August 2026. Developer Mill Hill Riviera Development. Completion registered for April 2026.

84%

Built, at the Land Department site inspection of 4 August 2026

6 months past its registered completion date

Completion date (Land Department)
April 2026
Finish at recent pace
December 2026
Construction started
October 2024
Registered with the Land Department
December 2024
Developer
Mill Hill Riviera Development
Community
Palm Deira
Units
60
Escrow bank
First Abu Dhabi Bank
Name in Arabic
اليجرو ريزيدنسز
Land Department project number
3404
Land Department site inspections
7

Schedule

Allegro Residences was registered to complete in April 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 5.0 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 August 2026

77%+7.5 pts

  • Allegro Residences construction site, Land Department inspection photo 1, 4 August 2026
  • Allegro Residences construction site, Land Department inspection photo 2, 4 August 2026
  • Allegro Residences construction site, Land Department inspection photo 3, 4 August 2026
  • Allegro Residences construction site, Land Department inspection photo 4, 4 August 2026

7 May 2026

70%+14 pts

  • Allegro Residences construction site, Land Department inspection photo 1, 7 May 2026
  • Allegro Residences construction site, Land Department inspection photo 2, 7 May 2026
  • Allegro Residences construction site, Land Department inspection photo 3, 7 May 2026
  • Allegro Residences construction site, Land Department inspection photo 4, 7 May 2026

5 March 2026

56%+22 pts

  • Allegro Residences construction site, Land Department inspection photo 1, 5 March 2026
  • Allegro Residences construction site, Land Department inspection photo 2, 5 March 2026
  • Allegro Residences construction site, Land Department inspection photo 3, 5 March 2026
  • Allegro Residences construction site, Land Department inspection photo 4, 5 March 2026

26 November 2025

35%+17 pts

  • Allegro Residences construction site, Land Department inspection photo 1, 26 November 2025
  • Allegro Residences construction site, Land Department inspection photo 2, 26 November 2025
  • Allegro Residences construction site, Land Department inspection photo 3, 26 November 2025
  • Allegro Residences construction site, Land Department inspection photo 4, 26 November 2025

4 August 2025

18%+12 pts

  • Allegro Residences construction site, Land Department inspection photo 1, 4 August 2025
  • Allegro Residences construction site, Land Department inspection photo 2, 4 August 2025
  • Allegro Residences construction site, Land Department inspection photo 3, 4 August 2025
  • Allegro Residences construction site, Land Department inspection photo 4, 4 August 2025

17 March 2025

6.1%+6.1 pts

  • Allegro Residences construction site, Land Department inspection photo 1, 17 March 2025
  • Allegro Residences construction site, Land Department inspection photo 2, 17 March 2025
  • Allegro Residences construction site, Land Department inspection photo 3, 17 March 2025
  • Allegro Residences construction site, Land Department inspection photo 4, 17 March 2025

29 November 2024

0%

  • Allegro Residences construction site, Land Department inspection photo 1, 29 November 2024
  • Allegro Residences construction site, Land Department inspection photo 2, 29 November 2024

All 51 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Mill Hill Riviera Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Allegro Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Allegro Residences be completed?
The completion date registered with the Dubai Land Department is April 2026. At the pace of its recent inspections the site would reach 100% around December 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Allegro Residences is built?
84%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 7 times since November 2024.
Is Allegro Residences delayed?
Yes. Its registered completion date of April 2026 has passed and the Land Department still lists it as under construction.
Who is building Allegro Residences?
The registered developer is Mill Hill Riviera Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Allegro Residences?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.